|
Ambiguous 'Arbitration' Provision Means Dispute must be Litigated
by John S. Mrowiec
Many standard construction industry contracts contain dispute
resolution provisions requiring arbitration of disputes. Some
such as the 1997 edition of the American Institute of Architects,
A201 General Conditions of the Contract for Construction provide
for mediation as a condition precedent to arbitration (see
AIA, A201, Paragraphs 4.5 & 4.6 (1997 ed.)).
Careless modification of the standard form, at best, might
result in confusion about the method of dispute resolution.
At worst, careless modifications could result in legal fees,
expenditures and wasted time on an issue that accomplishes
nothing toward resolution of a dispute.
An example of careless drafting resulting in the waste of
one year and legal fees spent merely to determine the dispute
resolution method is a new case, Showboat Marina Casino Partnership
v. Tonn & Blank Construction, 790 N.E.2d 595 (Ind. Ct.
App. 3d Dist., June 26, 2003).
Showboat, as owner, and Tonn & Blank, as contractor, entered
into a construction contract for the Harrah's East Chicago
Hotel in East Chicago, Ind. The contract was a "cost
plus" with a guaranteed maximum price. Showboat drafted
the contract.
Disputes arose concerning cost overruns and payments. The
contractor filed a complaint to foreclose a mechanics lien,
for breach of contract, and for unjust enrichment in Lake
County, Ind., court. The owner filed a motion to compel arbitration
citing the contract's "arbitration" clause.
The contract's "arbitration" clause actually was
entitled "Dispute Resolution." The essential portions
of the provision read:
A. Should the Parties to this Agreement have any dispute as
to any term, covenant or condition of this Agreement, the
Parties agree to meet in good faith and attempt to resolve
such dispute. If such informal resolution does not occur,
then either party may institute an arbitration as provided
below. Any and all of said disputes arising out of this Agreement,
and/or the Project shall be decided by a court of competent
jurisdiction, within the State of Indiana, with the prevailing
party in any action being entitled to full reimbursement of
all it's [sic] reasonable attorney fees and costs.
B. If a dispute arises out of or relates to this Agreement,
including any dispute about the existence of a breach of this
Agreement, and if the dispute cannot be settled through direct
discussions, the Parties agree to attempt to settle the dispute
in an amicable manner by mediation administered by the American
Arbitration Association under its Commercial Mediation Rules.
. . . Thereafter, any unresolved controversy or claim shall
be settled by arbitration administered by the American Arbitration
Association in accordance with its Commercial Arbitration
Rules, and judgment on the award rendered by the arbitrator(s)
may be entered in any court having jurisdiction thereof. (emphases
added).
Therefore, in the very same dispute resolution provision,
the contract provides that a party "may" institute
arbitration, "said disputes . . . shall be decided by
a court" and any controversy unresolved following mediation
"shall be decided by arbitration." So are disputes
to be arbitrated or to be litigated?
Courts frame the legal issue as: What did the parties intend
regarding resolution of disputes based on the language used
in the contract? The legal principles in such a case are:
1. Under Indiana law, the parties seeking to compel arbitration
have the burden of demonstrating the existence of an enforceable
arbitration agreement.
2. When construing arbitration agreements, every doubt is
to be resolved in favor of arbitration and the parties are
bound to arbitrate all matters, not explicitly excluded, that
reasonably fit within the language used.
3. However, parties are only bound to arbitrate those issues
that by clear language they have agreed to arbitrate.
4. Words, phrases, sentences, paragraphs and sections of a
contract cannot be read alone. The entire contract must be
read together and given meaning, if possible.
5. Any ambiguities in a contract are to be strictly construed
against the party who employed the language and who prepared
the contract.
6. In Indiana, to prevent resort to the courts, the agreement
must not only provide for arbitration but make such arbitration
a condition precedent to any litigation.
The trial court read the contract, found it to be ambiguous
and denied the owner's motion to compel arbitration. The owner
appealed.
The appellate court reviewed the contract and agreed with
the trial court: "The Agreement contains a definite ambiguity,
and we agree with the trial court that such ambiguity is to
be construed against Showboat, the drafter of the contract."
Therefore, the dispute is required to be litigated, as the
contractor wanted.
It is unclear whether the "prevailing party" would
be able to recover its legal fees if the dispute first had
been arbitrated with the arbitration award being subsequently
confirmed by a court. Perhaps that uncertainty motivated the
contractor to oppose arbitration even though doing so would
delay resolution. Maybe the contractor was uncomfortable with
arbitration under the "Commercial" Rules, rather
than the "Construction Industry" Rules of the AAA.
Or perhaps the contractor wanted the broader discovery that
litigation typically provides compared to arbitration.
What is clear is that one year past from the time of the
filing of the contractor's complaint until the parties definitively
knew how the dispute resolution process would proceed. The
cause of the wasted year and attendant legal fees was an owner
who drafted a contract carelessly. In fact, all signs suggest
that the drafting was a modification of a previously existing
dispute resolution provision.
John S. Mrowiec is a partner
with Chicago-based Conway & Mrowiec, a construction and
public contracts law and litigation practice. He may be reached
at (312) 658-1100. For information, go to the firm's Web site
at www.cmcontractors.com.
|