|
Unrepresented Mechanics Lien Claimants Committed Fatal Errors
by John S. Mrowiec
The requirements for service and filing of mechanics lien
claims are quite technical.
The requirements are governed by state statutes. The statutes
differ by state among Illinois, Indiana and Wisconsin.
Because of the differing statutes and their technical nature,
this column typically avoids discussing technical mechanics
lien requirements. Three recent cases have reported on claimants'
failure to satisfy requirements that resulted in loss of the
lien claim. In each of the three new cases, the claimant committed
the fatal flaw without the assistance of a lawyer. We thought
that fact made the cases newsworthy.
The case of Bale
v. Barnhardt, 2003 Ill. App. LEXIS 934 (4th Dist.
July 18, 2003), invalidated a contractor's claim. In Bale,
the claimant made a contract with the owner of property to
construct a pond. When the owner failed to pay, the contractor's
wife prepared and recorded a mechanics lien claim within four
months of Bale's last work.
Almost one year later, the contractor sued to foreclose the
lien claim. A mortgage lender moved to dismiss the suit. The
lender argued that the contractor had misdescribed the contract
in the lien claim and therefore the claim was invalid. The
trial court agreed and dismissed the suit. The contractor
appealed.
On appeal, the Bale
court summarized the requirements for an original contractor's
mechanics lien claim to be enforceable against a third party
encumbrancer, like the lender, under §7 of the Illinois
Mechanics Lien Act:
1. Filed within four months after the claimant's last work.
2. Verified by the claimant or an agent or employee.
3. Contain "a brief statement of the contract."
4. Set forth "the balance due."
5. Provide a "sufficiently correct description of the
lot, lots or tracts of land to identify the same."
The issue in Bale
was whether the contractor had correctly described the contract.
The contractor's wife had used a pre-printed mechanics lien
claim form. She wrote her name in the "Prepared by"
blank. Above the body of the claim, the contractor's wife
identified Martin L. Bale d/b/a Bale Excavating and Farm Drainage
as "Claimant." In the body of the claim, however,
she entered her own name as "Claimant" twice.
The Bale
court relied on two earlier cases for the proposition that
"the improper identification of a party to a contract
fails to provide the requisite 'brief statement of the contract'"
(Bale, 2003 Ill. App. LEXIS 934, *10.) The contractor argued
that the claim properly identified him at the top of the claim
form. The Bale court said the contradictory names for "Claimant"
meant the claim was unenforceable.
The contractor also argued that his complaint to foreclose
correctly described the contract so any error in the lien
claim was irrelevant. Not so, said the Bale
court, because the complaint was filed more than four months
after the contractor's last work. The party seeking to dismiss
the claim was a lender and was protected by the "four
month" rule.
One judge dissented. The dissenting judge argued that the
cases relied upon by the Bale
majority were different. In one of those cases, the claim
misidentified the non-contractor party to the contract. In
the other, the contractor's name, the contract date and even
whether the contract was oral or written were wrong. The Bale
dissent believed those cases clearly differed from a mistake
concerning a sole proprietor-contractor.
The Bale
case involved an original contractor. Under Illinois law,
subcontractors have additional requirements. The contents
and method of service of a subcontractor's notice were found
wanting in Seasons-4,
Inc. v. Hertz Corp., 338 Ill. (App.3d 565, 788
N.E.2d 179 (1st Dist., Mar. 28, 2003)). Despite actual receipt
of notice by the owner, the method of service was incorrect
in Rothers Construction,
Inc. v. Centurion Industries, Inc., (337 Ill. App.3d
629, 786 N.E. 2d 644 (4th Dist., Mar. 20, 2003)).
Often, an owner does not know who the subcontractors are or
how much the contractor might owe them. Therefore, in most
states there is a device for subcontractor notice to an owner
of the subcontractor's claim.
In Illinois, in addition to complying with Section 7 of the
Illinois Mechanics Lien Act, a subcontractor must serve a
notice under Section 24 of the Act. (The subcontractor need
not abide by Section 24 if the subcontractor is content to
rely on the contractor's sworn statement to owner given under
Section 5 of the Act for the amount due. Of course, some contractors
do not give the statement to owner, a subcontractor seldom
sees it anyway, unprocessed or disputed extras typically are
not listed and sub-subcontractors certainly are not listed
on the prime contractor's statement.)
Section 24 provides the subcontractor, within 90 days of subcontractor's
last work, shall "cause a written notice of its claim
and the amount due to be sent by registered or certified mail,
with return receipt requested, and delivery limited to addressee
only, to or personally served on the owner of record or his
agent or architect, or the superintendent having charge of
the building or improvement and to the lending agency, if
known . . ."
770 ILCS 60/24. Section 24 also provides a permitted form
of notice.
In Seasons-4,
an air conditioner supplier subcontracted with a prime contractor.
The subcontractor delivered units to a car rental agency on
a leasehold at O'Hare International Airport. The prime contractor
did not pay.
Within 90 days of delivery of the units, the subcontractor
delivered a letter by facsimile to the prime contractor with
a fax copy to the lessee's agent. The letter complained of
non-payment but did not assert a mechanics lien claim.
More than 90 days and more than four months after delivery
of the units, the subcontractor engaged a lawyer who prepared,
served and recorded a Subcontractor's Notice and Claim for
Mechanics Lien. Subsequently, the subcontractor sued.
The prime contractor did not defend but the lessee moved to
dismiss the subcontractor's count to foreclose a mechanics
lien. The trial court dismissed.
On appeal, the Seasons-4
appellate court affirmed that the subcontractor did not have
a valid lien claim against the lessee. The fact that lessee's
agent did not deny receiving the subcontractor's letter was
irrelevant to the Seasons-4
court. The court said the statute does not provide for facsimile
delivery of subcontractor mechanics lien notices.
In any event, the content of subcontractor's letter in Seasons-4
was insufficient: it never notified the lessee that the subcontractor
intended to assert a mechanics lien claim.
Notably, in Seasons-4,
the prime contractor never gave the lessee a Section 5 sworn
contractor's statement listing subcontractors and amounts
due them.
Rothers Construction
also involves an owner who knew that the subcontractor was
unpaid but, like in Seasons-4,
the subcontractor's lien claim still failed. In Rothers
Construction, a subcontractor on a grain bin and
material handling system project was not paid by the prime
contractor. The subcontractor spoke to the owner's representative
who, remarkably, told the subcontractor to record a mechanics
lien claim. The owner even referred the subcontractor to owner's
lawyer. Owner's lawyer partially completed a mechanics lien
claim form and forwarded it to the subcontractor.
The subcontractor recorded a mechanics lien claim within 90
days of subcontractor's last work. However, the subcontractor
never served a Section 24 Notice within 90 days of its last
work. Instead, the subcontractor served a notice many months
later, just before filing suit to foreclose the lien claim.
The owner moved to dismiss for failure to serve a Section
24 Notice to owner. The subcontractor argued that, under Section
25 of the Act, if the owner is not found within the county
where the improvement is constructed, recording the lien claim
is sufficient notice. The corporate owner's registered agent
was outside that county.
The Rothers
Construction trial court held that the subcontractor
should have given notice to owner under Section 24 under the
facts of this case. The subcontractor appealed.
The appellate court affirmed the trial court. The Rothers
Construction appellate court held that Section
25 only substituted for Section 24 when none of the owner,
owner's agent, architect or superintendent are within the
county of the improvement. Here, the owner's agent (not the
registered agent) participated in the project and was present
where the improvement was constructed. The lien claim failed.
This article discusses only a few of the pitfalls in preparing
and serving mechanics lien claims and notices. The case law
involving the technical requirements, their interpretation
and sometimes even additional "requirements," is
extensive. Although many mechanics lien claims appear to be
simple, many are not.
John S. Mrowiec is a partner
with Chicago-based Conway & Mrowiec, a construction and
public contracts law and litigation practice. He may be reached
at (312) 658-1100. For information, go to the firm's Web site
at www.cmcontractors.com.
|