|
Ambiguous Specifications: The Federal Duty to Inquire
by John S. Mrowiec
It is rare that the United States Supreme Court decides a
construction contract dispute. Undoubtedly, the most famous
construction contract case decided by the Supreme Court was
United States v. Spearin, 248 U.S. 132, 39 S.Ct. (1918).
Spearin established the now well-known principle of
the implied warranty of plans and specifications prepared
by or on behalf of an owner. The Spearin Doctrine,
as it is frequently called provides the following:
"If [a] contractor is bound to build according to plans
and specifications prepared by the owner, the contractor will
not be responsible for the consequences of defects in the
plans and specifications."
Recently, the Supreme Court was presented with the opportunity
to address the application of the Spearin Doctrine
to a modern, complex construction contract dispute concerning
contradictory and ambiguous plans and specifications on a
public works project. The Supreme Court declined to take the
case in KiSKA Construction Corp. v. Washington Metropolitan
Area Transit Authority, 321 F.3d 1151 (D.C. Cir. 2002),
cert. denied, 2003 U.S. LEXIS 7330 (Oct. 6, 2003).
The case is instructive nonetheless.
WMATA wanted to extend its Green Line subway under 14th Street
in Washington, D.C. WMATA hired a geotechnical engineering
consultant to assess the subsurface conditions. The geotechnical
consultant issued a report concluding that groundwater was
a significant problem at the site, "even . . . fairly
extensive dewatering" was not likely to be effective
and, therefore, "open face tunneling be strictly prohibited."
After issuing a second report, which confirmed the first,
the geotechnical consultant met with WMATA's Board of Engineers.
Thereafter, the geotechnical consultant issued a third report.
This third report characterized dewatering as "at best
going to be difficult" but permitted open face tunneling
in conjunction with extensive dewatering and a pre-support
grouting/ground improvement program. But the geotechnical
consultant warned WMATA that even the recommended grouting
would not permit open face tunneling if groundwater was not
depressed at least two feet below tunnel invert.
WMATA directed the consultant to design a dewatering system.
The consultant designed a system that included over three
hundred dewatering wells.
WMATA issued an Invitation for Bids to construction contractors
for a lump sum contract to construct the subway tunnel extension.
The bid documents did not disclose any of the geotechnical
consultant's reports. The design plans and specifications
included a specified grout system but did not include the
geotechnical consultant's 300+ dewatering well system. Instead
the contract specified a system of a different design calling
for 61 dewatering wells.
KiSKA Construction was the successful bidder at approximately
$43 million. (The decision does not report the amounts of
other bids.)
During construction, the contractor experienced a number of
difficulties with the specified dewatering system, which proved
ineffective, and the excavation methods required by the contract.
Although the contractor completed the project, it spent nearly
double the $43 million contract price.
The contractor sued. The contractor had five legal theories.
Before trial, the district court rendered three rulings that
resulted in limiting the trial to only two contract theories
each of which concerned the meaning of the plans and specifications.
The jury sided with the owner against the contractor. The
contractor lost its post-trial motion and then appealed to
the United States Appeals Court for the District of Columbia.
On appeal, the contractor's arguments may be summarized broadly
into two main issues: (1) Was this public owner required to
disclose to bidders the geotechnical reports (as contractor
contended) or was the failure to do so, under these facts,
protected by the doctrine of sovereign immunity (as owner
contended)? (2) Were the failures in the specified dewatering
system and grout hole system breaches of the implied warranty
of the plans and specifications entitling the contractor to
compensation under the Spearin Doctrine?
Space limitations require that this column truncate our discussion
of the various arguments and reasoning. The KiSKA Construction
appellate court first held that WMATA's decision not to include
the geotechnical reports in the bid package, under these facts
and a District of Columbia statute was not open to challenge.
The court recognized that an owner might owe a duty to contractors
to disclose knowledge that could affect performance of the
contract. In this "closer" case, however, the court
held the content of the bid package was the public owner's
discretionary decision susceptible to policy judgment and,
thus, was not subject to challenge.
On the second question, the contractor contended that the
Spearin Doctrine applied. After all, the contract required
"installation of the specified dewatering system as soon
as possible after notice to proceed." According to the
contractor, the owner had warranted that the specified dewatering
system would "maintain groundwater 2 ft. below invert"
by the following provision:
"For mined earth tunnels, additional wells beyond the
specified minimum dewatering system may be required to effectively
reduce hydrostatic pressure and control groundwater in soil
surrounding each tunnel in order to prevent the following:
A.) Heaving of the invert, blowups, hazardous seepage and
sudden flow of soil in tunnel face
B.) Loss of ground and surface subsidence
C.) Maintain groundwater 2 ft. below invert" (emphasis
added)
The owner, of course, emphasized the "additional wells
. . . may be required" language. Beyond that, another
paragraph in the same specification section warned:
"The designed dewatering system may not eliminate all
groundwater from the tunnel excavation. The Contractor shall
be prepared to support the tunnel face . . . and to handle
and convey groundwater from the tunnel to appropriate discharge
locations . . . additional dewatering wells may be required
based on the observed performance of the dewatering system."
The owner contended that the contract clearly alerted bidders
that the designed, specified dewatering system might have
to be supplemented by the contractor.
According to the owner, that meant the Spearin warranty
did not apply. The contractor argued it was senseless to use
the phrase "maintain groundwater 2 ft. below invert"
unless that was what the designed, specified system was to
do.
The crucial question then was: did the specification promise
the specified dewatering system would maintain the groundwater
two feet below the invert? The trial court ruled that the
specification was ambiguous on that point leaving the issue
for the jury to determine. The jury decided against the contractor.
On appeal, the KiSKA Construction appellate court agreed
that the specification was ambiguous. Unlike the trial court,
however, the appellate court said the specification was so
confusing and contradictory that the ambiguity was not "latent"
but "patent."
The appellate court emphasized that the language "maintain
groundwater 2 feet below invert" relied upon by the contractor
was one item in a three-item list following the word "prevent."
That was an "obvious" grammatical error.
In federal contracts, patent contract ambiguities are construed
against the contractor unless the contractor inquires about
the correct meaning of the terms at issue. An ambiguity is
"patent" if it is "glaring, substantial, or
patently obvious." If the ambiguity is "neither
glaring nor substantial nor patently obvious, however, and
therefore latent, the ambiguity is ordinarily construed against
the drafter" here, the government owner (KiSKA Construction,
321 F.3d at 1163-64).
The appellate court found the grammatical errors of one subsection
of the specification were "sufficiently obvious"
that the contractor had a duty to inquire regarding the true
meaning of the contract. By failing to do so, the contractor
"assumed the risk that the government would offer a reasonable,
but conflicting interpretation, which interpretation would
then be accepted by the court" (KiSKA Construction,
321 F.3d at 1164). Because the contractor failed to inquire
about the patent ambiguity, the Spearin Doctrine could not
apply: with hindsight, a $40 million error by the contractor
based on a grammatical error.
John S. Mrowiec
is a partner with Chicago-based Conway & Mrowiec, a construction
and public contracts law and litigation practice. He may be
reached at (312) 658-1100. For information, go to the firm's
Web site at www.cmcontractors.com.
|