News
 Association
 Law/Courtroom
 Building
 Design
 Infrastructure
 Personnel
 Illinois
 Indiana
 Wisconsin
 Submit News





Construction Law - January 2004

May a Mistaken Public Bid Be Withdrawn Without Penalty?
by John S. Mrowiec

Public owners of construction projects want assurance that the lowest responsive bidder will enter into the contract.

Bid security in cash or a bid bond is routinely required from public bidders. The Invitation to Bid usually provides that if a bidder is selected but refuses to enter into the contract, the bid security is forfeited as liquidated damages.

Bidding public construction contracts can be a chaotic experience, and mistakes sometimes occur in reaching the final bid price.

What remedies does a bidder have who discovers a bid error after the bids are opened? May the bid legally be corrected? If after correction the low bid is no longer low, may the bid legally be withdrawn? If the mistaken bid is withdrawn, does the withdrawing bidder forfeit its bid security to the public owner?

Issues of Bid Integrity

From the public owner's perspective, maintaining the integrity of the bidding process is important. If the low bidder legally may be allowed to correct an "error" too easily after bid opening, the taxpayer will suffer. Low bidders would be inclined to find "errors" to reduce the spread between the low and the second low bid after the second bidder's amount is known. Allowing post-opening corrections or withdrawals could be viewed as encouraging slipshod bidding practices.

From the low bidder's perspective, the public owner should not benefit from a true mistake resulting in an artificially low price. The purpose of public bidding of ensuring that the taxpayers pay the best prices would be thwarted. Bidders would be reluctant to bid or would include unwarranted contingencies, if they would be bound despite an inadvertent error. Higher bid prices would be the result.

A balance, then, must be struck between allowing corrections or withdrawals for just any error and holding bidders to their bid prices, no matter the circumstance.

Case law has discussed the issue of bid mistakes under the theory of "unilateral mistake." Some states have statutes that provide relief for a mistaken bid.

Whether under the case law or under statute not all mistaken bids may be corrected or withdrawn. The language permitting correction or withdrawal in the case law or statute varies from state to state. The controlling questions usually concern (1) whether the bidder acted quickly to notify the government of the error, (2) whether the mistake was one of judgment (which usually will not be permitted to be corrected) or instead a "clerical" error (which might be permitted to be corrected), and (3) the degree of care exercised by the bidder to attempt to avoid mistakes.

Wisconsin's Statute

Wisconsin has a statute permitting mistaken bids to be withdrawn before bid opening and, under certain circumstances, after bid opening to correct a mistaken bid, Wis. Stat. §66.0901(5). The application of the Wisconsin statute was recently at issue in James Cape & Sons Co. v. Mulch, 2003 Wisk. App. 1013 (4th Dist., Oct. 30, 2003).

In James Cape & Sons one sees a fairly typical bidding scenario. The Wisconsin Department of Transportation advertised for bids of a highway interchange. That project's bids, along with other projects' bids, were to be submitted and opened at 9 a.m. on a designated date.

Prospective bidders, including the bidder, assembled personnel in hotel rooms near the government's office. This bidder's team had eight people equipped with computers, printers, project folders and telephones.

The bidder's team worked the prior day and into the early morning hours receiving subcontractor proposals and integrating some of them into the bidder's final bid. The proposals were maintained in hard copy form and integrated into computer spreadsheets.

One potential subcontractor submitted its proposal at 6 a.m. the morning the bids were due. The subcontractor had the low price for a designated scope of work, and the bidder integrated the subcontractor's price into the tentative bid computer spreadsheet.

Less than 30 minutes before the bid deadline, the subcontractor notified the bidder - and two other bidders - that its proposal was mistaken on a unit price. The revised unit price required an upward revision of $450,000. The bidder compared the revised proposal with another proposal for that work scope and determined the subcontractor still had the low price.

For some reason, the subcontractor's revised price was not integrated into the computer spreadsheet. The bidder did make one handwritten change to the sheet before submitting the final bid price. However, the bidder failed to note that the revised price from the subcontractor had not been corrected. The bidder submitted its final bid without including the correction.

Other bidders, however, correctly included the subcontractor's revised higher price and mark-up. The bidders submitted bid security as required by invitation to bidders in the form of bid bonds of $100,000 in penal sum.

The bidder in question was low. The bidder recognized the error soon after the bids had been opened and notified the owner in writing that day. The bidder's letter explained the circumstances and attached copies of documents supporting the basis of the mistake. The bidder requested a correction but recognized that a correction would mean the bidder no longer would be low. Alternatively, the bidder asked to withdraw the bid and that the owner not claim upon the bidder's bid bond.

The owner responded that neither the statute nor specifications permitted a correction after bid opening. The owner advised that it would consider the alternative request to withdraw the bid but, if withdrawn, the bidder would forfeit the $100,000 bid bond unless the bidder proved that the "error" was "free from carelessness, negligence or inexcusable neglect."

The bidder replied that the error was clerical and entitled the bidder to withdrawal and return of the bond. The owner notified the bidder that the owner was awarding to the bidder at the bid price. The bidder replied that it would not execute the contract because of the error that "was by a clerical person who was finalizing our bid and was not performed by someone who was reviewing the plans, specifications or making judgments as to the cost of the work."

The owner then notified the bidder that it had "annulled" the contract award to the bidder, would award to the second low bidder but that the bidder would forfeit the bid security.

The bidder sued seeking a judgment declaring that the bidder was entitled to correct its bid and be released from its bid bond. The bidder and the owner moved for summary judgment.

The Court's Determination

The trial court determined there were no material facts in dispute and that under the Wisconsin statute, the owner should have permitted the bid to be corrected before contract award. The trial court ruled in the alternative that if the bidder was required by statute to show freedom from carelessness, negligence or inexcusable, the bidder had done so. Accordingly, the trial court ordered the owner to return the bid security. The owner appealed.

On appeal, the appellate court first determined that the Wisconsin statute permitted correction of bid after opening and prior to award but required a contractor to prove freedom from carelessness, negligence or inexcusable neglect.

But are not all "mistakes" in some way careless or negligent? If one must be "free" from "carelessness," when could a mistake ever be corrected? After reviewing the case law, the James Cape & Sons appellate court reasoned "some omissions on the part of a bidder, although representing some degree of carelessness, negligence or neglect, may still be excusable" (James Cape & Sons, 2003 Wisc. App. 1010, 34.) The appellate court said the focus should be on the "nature of the error."

According to the Wisconsin court, errors which are "mechanical" or "clerical" in nature might be excusable; they should be distinguished from those errors "involving a lapse in the exercise of professional judgment" which likely would not be excusable (James Cape & Sons, 2003 Wisc. App. 1013, 36.)

Although the appellate court noted that the bidder, "could have (and perhaps 'should have') caught the error" prior to bid submission, that did not mean the bidder's procedures for final bid preparation and submission represented a failure to exercise ordinary care or inexcusable neglect. Therefore, the appellate court affirmed the trial court's holding that the bid security should be returned (James Cape & Sons, 2003 Wisc. App. 1013, 39.)

Indiana, Illinois Statutes

Indiana has a statute regarding bid mistakes, Burns Ind. Code Inn. §5-/22-7-10. The Indiana statute merely allows governmental bodies to adopt rules or establish policies to allow correction or withdrawal of erroneous bids before or after award and cancellation of awards or contracts based on mistake. Under the Indiana statute, in the absence of a rule or policy otherwise, the purchasing agency must provide a written decision.

Indiana courts have permitted withdrawal of a bid and return of bid security where the facts surrounding the mistake showed the bidder "was not negligent and careless in submitting his bid" (Board of School Commissions v. Bender, 36 Ind. App. 164, 72 N.E. 154 (1904) (bidder inadvertently failed to include amounts from one sheet of his multiple sheet pre-bid worksheet in final lump sum price)).

Illinois applies the common law doctrine of unilateral mistake. A bid may be corrected if the bidder can show by clear and positive evidence that (a) the mistake was material, (b) it occurred despite exercise of reasonable case, (c) it would be unconscionable to enforce the bid containing the mistake and (d) the owner can be placed in status quo after the correction. (See Wil-Freds, Inc. v. Metropolitan Sanitary District, 57 Ill. App. 3d 16, 21, 372 N.E. 2d 946, 951 (1st Dist. 1978)).

Generally, bidder relief is refused for errors in judgment and allowed for clerical or mathematical mistakes. Yet, "the facts surrounding the error, not the label, i.e. 'mistake of fact' or 'mistake of judgment' [will] determine whether relief is granted" (Wil-Fred's, Inc., 372 N.E. 2d at 953 (prime contract bidder who followed its bid review procedures could rescind awarded contract and require bid security returned from error in subcontractor's misunderstanding of specifications)).


John S. Mrowiec is a partner with Chicago-based Conway & Mrowiec, a construction and public contracts law and litigation practice. He may be reached at (312) 658-1100. For information, go to the firm's Web site at www.cmcontractors.com.


 Click here for more Construction Law News >>



advertisement


 


Sponsors

© 2008 The McGraw-Hill Companies, Inc.
All Rights Reserved