|
Two Views of the Same Contractual Defenses On Increased Labor Cost Claims
by John S. Mrowiec
Sophisticated subcontracts are usually written by prime contractors
to attempt to maximize the general contractor's flexibility
to maintain the project schedule while minimizing the subcontractor's
ability to assert claims for delay, acceleration or disruption
costs. A common combination of subcontract clauses would include
the following:
(1.) Acknowledging that the subcontract time includes consideration
of hindrances and delays
(2.) Allowing the general contractor to reschedule subcontractor's
work
(3.) Requiring subcontractor to add workforce or to accelerate
at contractor's direction
(4.) Excluding damages for delay
(5.) Providing contractor (or others) with final and binding
decision-making authority on subcontractor claims
(6.) Setting short deadlines for submission of subcontractor
claims and for protesting decisions on those claims
How effective are these provisions? It can be difficult to
predict the outcome.
The answer often depends on the facts of the particular case.
Two courts may read the provisions as applied to the very
same facts completely differently. A textbook example is the
recent case of Atlantic
Coast Mechanical v. R.W. Allen Beers Construction,
2003 Ga. App. LEXIS 1468 (3d Div., Nov. 24, 2003), on
reconsid., 2003 Ga. App. LEXIS 1573 (3d Div. Dec.
15, 2003).
Atlantic Coast Mechanical was the HVAC and plumbing subcontractor
to Beers Construction, the general contractor. The project
was the Children's Medical Center in Augusta, Ga.
The Subcontractor submitted a Request for Equitable Adjustment
seeking payment of increased labor costs arising from alleged
disruptions to the Subcontractor's work by the general contractor.
Subcontractor claimed it was forced to perform its work in
"a radically different manner, method and sequence than
that reflected in the project schedules or contemplated by
[subcontractor] at the time it bid on the project."
The REA listed a common litany of disruptions. Subcontractor
claimed the following:
(a.) The concrete operations on the project were performed
late and out of sequence and reshores were not removed as
scheduled. As a result, Subcontractor had only restricted
access to work areas and could not rough-in the overhead pipe
and equipment using rolling scaffolds and manlifts, as planned.
(b.) When the restricted areas became more accessible, Subcontractor's
work was constructively accelerated.
(c.) General Contractor required Subcontractor to work on
most floors simultaneously which required Subcontractor to
more than double the size of its crews and required the oversized
crews to work overtime frequently.
(d.) General Contractor also instructed other subcontractors
to work on floors where Subcontractor was working, further
obstructing Subcontractor's access to ceiling work areas.
(e.) General Contractor allowed other subcontractors to stockpile
drywall, curtain wall and other materials on the floors, further
restricting Subcontractor's access to work areas.
Subcontractor claimed General Contractor's denial of Subcontractor's
access to work areas, interference with Subcontractor's work
and failure to schedule and manage other subcontractors properly
resulted in a significant increase in labor costs.
The General Contractor denied the Subcontractor's REA in writing.
The Subcontract contained the following provisions:
Article 3(b): Time is of the essence of this Trade Contract.
In agreeing to complete the Work within the times and sequences
herein mentioned, Subcontractor represents that it has taken
into consideration and made allowances for all hindrances
and delays incident to its Work.
Article 10(b): Subcontractor shall comply with any schedule
requirements imposed upon General Contractor in its Agreement
with the Owner. General Contractor shall have the right to
decide the time, order and priority in which the various portions
of Subcontractor's Work will be performed and other matters
relative to the time and orderly conduct of Subcontractor's
Work, if in General Contractor's judgment, such actions are
necessary to assure compliance with the scheduling requirements
imposed upon General Contractor in its Agreement with the
Owner.
Article 10(c): Subcontractor shall at all times supply and
promptly pay for adequate tools, appliances, equipment, a
sufficient number of properly skilled workmen and a sufficient
amount of materials and supplies of specified quality to efficiently
and properly prosecute the Work in accordance with General
Contractor's Schedule, and any modifications thereto issued
by General Contractor, in order to achieve the Project completion
date established by General Contractor. Subcontractor shall
at all times give due consideration to the fact that other
work is dependent upon Subcontractor's proper and timely completion
of its Work.
Article 2: "Subcontractor agrees to be bound to General
Contractor by all of the terms of the Agreement between General
Contractor and the Owner (except for the payment provisions)
and Subcontractor assumes toward General Contractor the obligations
and responsibilities that General Contractor assumes toward
the Owner. General Contractor shall have the benefit of all
rights, redress and remedies against Subcontractor which the
Owner has against General Contractor under its Agreement with
General Contractor."
The contract between the General Contractor and the project
owner stated the following:
In the event of any delay, not the fault of General Contractor,
General Contractor shall be entitled to an extension of time
for completion only, and shall not be entitled to any additional
payment on account of such delay. Without limiting the foregoing
. . . , General Contractor shall not be entitled to payment
or compensation of any kind from the Owner for direct, indirect
or impact damages, including but not limited to costs of acceleration
arising because of hindrance or delay from any cause whatsoever,
whether such hindrances or delays be reasonable or unreasonable,
foreseeable or unforeseeable, or avoidable or unavoidable;
provided, however, that this provision shall not preclude
recovery by General Contractor of damages for hindrances or
delays due solely to fraud or bad faith on the part of the
Owner or his agents.
Article 14(b): Any dispute concerning a question of fact arising
under this Agreement which is not resolved shall be decided
by General Contractor, and General Contractor shall reduce
its decision to writing and furnish a copy thereof to Subcontractor.
The decision of General Contractor shall be final and conclusive,
unless within forty-eight (48) hours from the date of receipt
of such decision, Subcontractor issues written notice to General
Contractor contesting same. If Subcontractor does not contest
General Contractor's final decision within the time period
noted above, Subcontractor shall be deemed to have waived
any right to contest that decision. Subcontractor shall carry
on the Work and comply with its performance and scheduling
obligations under this Agreement despite the existence of
any dispute or legal proceedings, unless otherwise agreed
in writing by the parties hereto.
The Subcontractor sued. The General Contractor moved for summary
judgment.
The Contractor's arguments were as follows:
(a.) Subcontractor had waived the claim by failing to object
to Contractor's letter denying the claim within 48 hours of
receiving the letter
(b.) The subcontract provisions regarding schedule and hindrances
barred the claim
(c.) The incorporated "no damages for delay" provision
from the prime contract barred the claim. (The General Contractor
also had a "change order waiver" argument but space
limitations prevent my discussion of that argument.)
The trial court agreed with the Contractor and entered summary
judgment dismissing Subcontractor's complaint. The Subcontractor
appealed.
The
Atlantic Coast Mechanical Appellate court disagreed
with all the Contractor's arguments and reversed the trial
court's judgment. First, regarding the 48-hour rule, the Atlantic
Coast Mechanical appellate court emphasized that
the provision expressly was limited to disputes "concerning
a question of fact." In its letter, the Contractor argued
that Subcontractor's REA was barred by the Subcontract's provision
and did not consider the merits of the claim. The appellate
court said that Contractor had not considered the dispute
as a question of fact and, by its "plain language,"
the Subcontract's "48 hour" provision did not apply.
Regarding the schedule and hindrances subcontract provisions,
the Atlantic
Coast Mechanical court carefully reviewed those
provisions as well. The provision that acknowledged there
would be hindrances and delays, the appellate court held,
"applies only to hindrances and delays that [Subcontractor]
could have foreseen upon entering the contract." Subcontractor
had submitted evidence in opposition to the Contractor's summary
judgment motion that the disruptions and hindrances were far
in excess of what normally could be expected when the subcontract
was executed.
In addition, the Atlantic
Coast Mechanical appellate court noted that the
provision was silent regarding Subcontractor's entitlement
to additional compensation for unanticipated labor costs caused
by General Contractor's disruption. Similarly, concerning
the provisions allowing the General Contractor to alter the
time, order and priority of Subcontractor's work, the appellate
court noted that the provisions "do not address whether
[Subcontractor] is entitled to assert a claim for additional
compensation when [Subcontractor] incurs substantial unanticipated
labor costs in trying to meet the schedule(s) established
by [General Contractor]."
Addressing the incorporated "no damages for delay"
clause, the Atlantic
Coast Mechanical appellate court noted there was
other language in the subcontract that permitted compensation
for disruption and delays not the fault of Subcontractor "to
the extent, but only to the extent [General Contractor] actually
recovers compensation for same from the Owner." The Subcontract
contained a provision that, in the event of any conflicts
between the subcontract agreement form and the incorporated
prime contract, the subcontract agreement would govern. The
Atlantic Coast Mechanical appellate court
held that the subcontract language allowing compensation under
some circumstances then trumped the incorporated prime contract's
"no damages for delay" clause. The appellate court
did not explain whether Subcontractor's rights depended on
payment to General Contractor by Owner.
The Atlantic
Coast Mechanical appellate court sent the case
back to the trial court for trial. Two courts; same facts;
same contract; opposite results.
John S. Mrowiec is a partner
with Chicago-based Conway & Mrowiec, a construction and
public contracts law and litigation practice. He may be reached
at (312) 658-1100. For information, go to the firm's Web site
at www.cmcontractors.com.
|