|
The Pitfalls of Mechanics Liens for Tenant Work
by John S. Mrowiec
Many owners, contractors and others in the construction industry
assume that an unpaid debt for work on a construction project
always may be secured by a mechanics lien on the real estate
provided the technical notice and deadline requirements are
met. Not so.
Especially in the context of contracts with tenants for improvements
to leased realty, the rules can be restrictive. Statutes vary
from state to state. Most states' laws impose special proof
requirements on tenant improvement lien claimants who want
their liens to attach to a lessor's real property.
Purdue Project
The difficulty of establishing a mechanics lien in the context
of tenant improvement work under the Indiana mechanics lien
statute, I.C. 33-28-3-1, is shown by the recent case of Cho
d/b/a Ace Construction & Interior Design v. Purdue Research
Foundation, 2004 Ind. App. LEXIS 289 (2d Dist.,
Feb. 26, 2004).
A tenant had leased six rooms at the Purdue Technology Center
in West Lafayette, Ind. The Lease provided that Tenant was
not to make alterations or improvements to the leased space
without the "prior written consent" of the lessor,
Purdue Research Foundation.
After entering into the lease, the tenant expressed an interest
in leasing nearly 10 times more than the original space to
construct a clean room to manufacture computer chips. The
lessor advised the tenant that the lessor would agree to the
construction of a clean room in the additional space provided
the lessor and tenant reached agreement on a lease for the
additional space.
While lease negotiations continued, the tenant entered into
a contract with Ace Construction to design, procure equipment
and construct the clean room at the Technology Center. Under
the clean room engineer-procure-construct agreement, the contract
would "professionally manage" the project, procure
required subcontracting services and have a technical crew
perform equipment installation.
The lessor did not participate in negotiating or drafting
of the EPC agreement and did not sign or initial it. The tenant
never provided lessor with the details or a copy of the agreement.
The contractor commenced its contract design services. The
lessor advised tenant that tenant could not commence actual
construction until lessor had reviewed the plans for potential
impact on other tenants and a new lease was executed. The
lessor also informed the contractor that construction could
not commence without lessor's approval.
Eventually, the contractor requested the lessor's development
director to consent to contractor's performance of ceiling
tile and grid demolition and installation of metal frame in
the proposed clean room space. Lessor consented to the demolition
but not to the new installation.
The demolition involved removal of air conditioning ductwork,
light fixtures and wiring. The contractor self-performed the
demolition.
After completion of demolition, the contractor requested the
lessor to review and approve the plans so that the governing
authority's design approval could be obtained.
The lessor reviewed and commented on the plans. However, the
lessor declined to sign approval of any construction documents
because lease negotiations had not concluded.
In addition to the demolition and design work, the contractor
purchased equipment and materials and placed partially completed
manufacturing orders that could not be canceled at a total
cost of more than $370,000. Ultimately, lessor and tenant
never agreed to a lease for the clean room space.
The contractor filed a notice of mechanics lien with the county
recorder. The contractor later filed suit to foreclose the
lien claim. The lessor moved for summary judgment.
Suit Results
The lessor argued that there could be no lien on its property
because the lessor had never actively consented to the improvements
on which the lien was based. The trial court agreed with the
lessor and dismissed the contractor's complaint. The contractor
appealed.
On appeal, the appellate court discussed the requirements
in Indiana to establish a mechanics lien on a lessor's property
arising from work for a tenant. In Indiana, before a mechanics
lien can attach, the landowner must consent to the improvements
on which the lien is based. This consent "must be more
than inactive or passive consent" and the lien claimant's
burden of proof is "especially important when the improvements
are requested by someone other than the landowner" Cho,
2004 Ind. App. LEXIS 289, *13 citing Stern
& Son, Inc. v. Gary Joint Venture, 530 N.E.2d
306, 307 (Ind. Ct. App. 1988). Absent the owner's active consent,
the lien claimant's interest attaches only to the tenant's
interest.
In Cho,
there was no question that the lessor "was aware of the
construction" but, in Indiana, "this awareness nevertheless
does not establish the sort of active consent needed to maintain
a mechanics lien" Cho,
2004 Ind. App. LEXIS 289, *15. In Indiana, the active consent
focus:
"is not solely on the degree of the owner's active participation
in the decisions and the actual construction. Instead, the
focus is also on how closely the improvement in question resemble
a directly bargained-for-benefit" Cho,
2004 Ind. App. LEXIS 289, *16.
The Cho
court found that the minor demolition consented to by the
lessor provided no direct benefit to the lessor. Rather, the
lessor spent to replace the removed ceiling when the clean
room project did not proceed. Obviously, the lessor did not
benefit from the design and equipment for the project never
installed. Therefore, the Cho
appellate court held no lien could attach to the lessor's
interest.
The lesson of the Cho
case for contractors is when performing tenant work, do not
get too far into the process without evidence of a signed
lease for the location of the planned improvements and Owner
consent to the improvements. Such a contractor might not have
a lien on the lessor's improvements.
Addendum
In the May 2003 column we discussed an Indiana intermediate
appellate court case holding that a subcontractor was not
bound to arbitrate with the prime contractor. In that case,
the subcontract lacked an express arbitration clause and the
incorporation by reference clause was limited to "as
applicable to the work stated" in the subcontract. The
Indiana Supreme Court recently affirmed the appellate court
in MPACT
Construction Group, LLC v. Superior Concrete Constructors,
Inc., 2004 Ind. LEXIS 94 (Feb. 4, 2004).
John S. Mrowiec is a partner
with Chicago-based Conway & Mrowiec, a construction and
public contracts law and litigation practice. He may be reached
at (312) 658-1100. For information, go to the firm's Web site
at www.cmcontractors.com.
|