|
Mechanics Liens on Multiple Structure, Multiple Owner Project
by John S. Mrowiec
In a past column, we have discussed the difficulties surrounding
mechanics liens on a lessor's property arising from tenant
work, The
Pitfalls of Mechanics Liens for Tenant Work (April
2004) and the impact of failure to satisfy some of the technical
requirements of a mechanics lien statute, Unrepresented
Mechanics Lien Claimants Committed Fatal Errors
(Oct. 2003). A new case involves another difficult problem
- perfecting a mechanics lien on a multiple-structure, multiple-owner
project.
The case of Ehlers
Construction, Inc. v. Timbers of Shorewood, L.P.,
2004 U.S. Dist. LEXIS 3886 (N.D. Ill. March 11, 2004) involved
construction of two attached structures on adjoining parcels
owned by different legal owners but with a common street address.
The general contractor, Ehlers Construction Inc., entered
into two separate construction contracts.
The first was to construct a 90-unit assisted living project
on land known as Lot 147A (the "AL Project"). The
owner of the AL Project was "Timbers of Shorewood - AL,
L.P."
The second contract was to construct a 96-unit senior citizen
independent living facility on land known as Lot 147B (the
"IL Project"). The owner of the IL Project was "Timbers
of Shorewood, L.P."
The AL and IL projects were attached. Not only were the two
projects owned by owners with almost identical names but the
two projects had the identical street address of 1100 N. River
Rd.
The general contractor entered into eight separate subcontracts
with a subcontractor, Avenue Inc. Some of the subcontracts
related to the AL Project, some to the IL Project.
The subcontractor claimed an amount due and recorded a single
mechanics lien claim. The subcontractor's mechanics lien claim
was a "blanket lien" on both of Lots 147A and 147B.
The lien claim did not allocate separate amounts owing to
each lot.
The general contractor also claimed amounts due from the owners
under the two prime contracts and recorded two separate mechanics
lien claims, one for each separate contract and appropriate
lot. The general contractor filed suit against the two owners
to foreclose its two lien claims.
The subcontractor intervened and sought to foreclose its single
lien claim. The subcontractor's complaint said it was owed
under "contract or contracts" but did not specify
under which subcontract or subcontracts the amount was owed.
The general contractor moved to dismiss the count of the subcontractor's
complaint that sought to foreclose the subcontractor's lien
claim. The general contractor argued that the subcontractor's
mechanics lien claim was invalid because the subcontractor's
lien claim (1.) was an improper blanket lien on two parcels
owned by two separate owners; (2.) was a single lien relating
to eight separate subcontracts on two separate projects; (3.)
did not set forth the proper legal description; (4.) misdescribed
the owners; and (5.) did not set forth the last date of work
associated with each project.
The subcontractor apparently did not deny these issues but
argued they were innocent errors with no effect on the validity
of the subcontractor's lien.
The suit had been filed in federal court. The federal court
applied the Illinois Mechanics Lien Act as the governing substantive
law on the mechanics lien foreclosure issues.
Court's Ruling
As a touchstone, the federal court noted that the Mechanics
Lien Act is strictly construed regarding the requirements
for establishing a valid mechanics lien.
Applying the Mechanics Lien Act, the court held that the subcontractor's
unallocated, blanket lien on two parcels in this case was
invalid.
The Ehlers
Construction court recognized that blanket liens
are appropriate when a single owner enters into a single contract
to construct or improve more than one building on one or more
lots. However, here, the subcontractor's lien failed because
the subcontractor performed work under multiple subcontracts
on two separate parcels owned by two separate entities.
Next, the Ehlers
Construction court held the subcontractor's lien
claim also was invalid because it failed to include a brief
statement of the contract as required by section 7 of the
Illinois Mechanics Lien Act. The court's reasoning here is
somewhat confusing.
The court conceded that the subcontractor had served notice
to both owners. However, the subcontractor's lien claim mentioned
only one owner in its description of the contract. Even though
the claimant was a subcontractor (whose subcontract is with
a prime contract), the Ehlers
Construction court held the failure to name the
other owner in the description of the contract was a fatal
error.
Lastly, the federal court held the subcontractor's lien claim
was defective because it purported to attach to both of Lots
147A and 147B when the subcontractor mentioned only one owner
in the lien claim's description of the contract. By naming
only one owner in the contract description, all the court
could assume from the lien claim is that the amount owing
related solely to that owner's lot, not the other lot. When
the subcontractor liened both lots, the court held that the
subcontractor had overliened and according to the court, had
misdescribed the property. The subcontractor's mechanics lien
claim was ruled invalid on both lots.
The Ehler
Construction court decision teaches that a subcontractor
needs to perform some investigation about who the owners are
when building on a multiple owner, multiple parcel site. The
careful claimant liens only the parcel owned by the owner
from whose contract amounts remain due. All lien claimants
must use special care in the multiple parcel, multiple owner
context.
Update on Local 150
In a past issue, we discussed some of the ongoing litigation
concerning the efforts of Local 150 of the International Union
of Operating Engineers to organize personnel of geotechnical
and construction materials engineering firms, Labor Union
Disputes Regarding Engineering Firms (Feb. 2004). Recently,
the United States Court of Appeals affirmed a National Labor
Relations Board order in favor of an employer, Terracon Inc.,
against Local 150, holding that the employer had not voluntarily
recognized the union as the bargaining representative for
the employer's drillers and drill helpers. International Union
of Operating Engineers, Local 150 v. National Labor Relations
Board, 2004 U.S. App. LEXIS 4859 (7th Cir., March 16, 2004).
John S. Mrowiec is a partner
with Chicago-based Conway & Mrowiec, a construction and
public contracts law and litigation practice. He may be reached
at (312) 658-1100. For information, go to the firm's Web site
at www.cmcontractors.com.
|