|
Unconditional Lien Waivers in Advance of Payment: A Dangerous Practice in Wisconsin
by John S. Mrowiec
Owners want to receive mechanics lien waivers in exchange
for construction project progress and final payments. Often,
contractors and subcontractors must submit the waivers along
with their respective pay applications in advance of the payment.
Sometimes the payment application - lien waiver - payment
process is conducted by use of a title company escrow. Other
times, no escrow is used.
If the owner or contractor does not pay, is a subcontractor's
mechanics lien waiver tendered in advance of the requested
payment still a valid waiver? The subcontractor might have
waived its mechanics lien rights even without payment. The
particular result depends on the relevant state law and factual
circumstances.
The new case of Tri-State
Mechanical, Inc. v. Northland College, 2004 Wisc.
App.
LEXIS 313 (3d Dist., April 13, 2004), shows how dangerous
it can be to tender a lien waiver in advance of payment in
Wisconsin. In Northland
College, the owner, a college, contracted with
Frank Tomlinson Co., the prime contractor, to build a new
science building. The prime contract was a cost plus with
a guaranteed maximum price contract.
The prime contractor entered into a subcontract with Wynn
O. Jones & Associates Inc. as subcontractor. The subcontractor
was to install science laboratory casework materials. The
subcontract was for a lump sum price. The subcontract required
that the subcontractor furnish a properly executed release
and waiver of liens as "an explicit condition precedent
to the accrual of subcontractor's right to final payment."
The subcontractor completed its work and submitted the required
final waiver.
Although the owner paid the prime contractor "the full
contract price of nearly $5 million," the prime contractor
never paid the subcontractor. In fact, the prime contractor
went out of business.
The subcontractor timely filed its mechanics lien claim. Another
subcontractor, Tri-State Mechanical, also filed a lien and
initiated a suit. The subcontractor counterclaimed to foreclose
its lien claim against the owner's real property and improvements
and against the owner for "unjust enrichment."
Owner's Defense
The owner defended against the subcontractor's mechanics
lien foreclosure, arguing the subcontractor's final lien waiver
waived all mechanics lien rights. After a bench trial, the
court ruled that the subcontractor could not maintain a lien
claim because of the lien waiver. The court also concluded
that there was no "unjust enrichment' of the owner because
the owner had paid the full contract price to the prime contractor.
The subcontractor appealed. On appeal the subcontractor argued
that the Wisconsin statute regarding construction liens voided
the construction lien waiver provision in its subcontract
and, therefore, the lien waiver the subcontractor tendered
also was void.
The Northland
College appellate court analyzed the Wisconsin
statute. The Wisconsin statute provides:
"The following provisions in contracts for the improvement
of land in this state are void:
(1) Provisions requiring a contractor, subcontractor or material
supplier to waive his or her right to a construction lien
or to a claim against a payment bond before he or she has
been paid for the labor or materials or both that he or she
furnished (Wisc. Stat. §779.135(1))."
The appellate court agreed that the Wisconsin statute voids
provisions in construction contracts requiring a subcontractor
to waive its right to a construction lien before payment.
The Northland
College court also agreed "the policy behind
the statute was to ensure that contractors and subcontractors
were paid for their work before they were required to produce
a lien waiver" Northland
College, 2004 Wisc. App. LEXIS 313, *5.
However, the Northland
College court disagreed with the subcontractor's
argument that the statute consequently made the subcontractor's
lien waiver void. The Northland
College court cited another provision of the Wisconsin
statute:
"Any document signed by a lien claimant and purporting
to be a waiver of construction lien rights under this subchapter,
is valid and binding as a waiver whether or not consideration
was paid therefore and whether the document was signed before
or after the labor or material was furnished or contracted
for . . . A lien claimant or potential lien claimant of whom
a waiver is requested is entitled to refuse to furnish a waiver
unless paid in full for the work or material to which the
waiver relates (Wisc. Stat. §779.05(1))."
Reading the two sections, .135 and .05(1) together, the court
instead saw the statute as providing the following:
"A subcontractor facing a void construction lien waiver
provision with a choice: it can either tender a lien waiver
prior to being paid or refuse to do so until it is paid. By
giving the subcontractor a choice, the legislature has essentially
made a policy decision that endorses whatever course of action
the subcontractor takes"
Northland
College, 2004 Wisc. App. LEXIS 313, 5-6. By furnishing
the waiver, the Northland
College court held, the subcontractor chose to
accept the risk of nonpayment.
A Look at Illinois, Indiana
Citing an Illinois case, the subcontractor also argued that
the lien waiver should be ineffective because the owner could
not have reasonably relied on it. Without discussing any application
to the facts of the case, the Northland
College court rejected outright the concept as
one inappropriate for judicial, rather than legislative, action.
The subcontractor had effectively waived its construction
lien under Wisconsin law by furnishing the unconditional final
lien waiver even though the subcontractor was not paid.
The Illinois Mechanics Lien Act provides agreements to waive
any right to enforce or claim a lien where the agreement is
in anticipation of and in consideration for the awarding of
a contract or subcontract "unenforceable" 770 ILCS
60/1.1.
An Illinois court has held that the statute made unenforceable
a prime contractor's insistence on a contract provision requiring
a final waiver in exchange for a payment which the subcontractor
viewed as only partial payment because of disputed extras
in Brown
& Kerr, Inc. v. American Stores Properties, Inc.,
306 Ill. App. 3d 1023, 715 N.E. 2d 804 (1st Dist. 1999). Illinois
courts will enforce a final waiver of lien even without payment
but recognizing the custom and practice in the industry of
tendering lien waivers in advance of payment, the claimant
may avoid the effect of the waiver if there was not good faith
reliance on the waiver, Fisher
v. Harris Bank & Trust Co., 154 Ill. App. 3d
79, 506 N.E. 2d 418 (2d Dist. 1987).
In Indiana, the statute since July 1, 2002, provides that
a contract provision is void if it requires waiver of a right
to lien, Ind. Code §32-38-3-16. Indiana case law prior
to the Indiana legislature's adoption of the prohibition on
contract provision's waiving of lien rights required consideration
(usually payment) to support a waiver of lien (unlike the
case law in Wisconsin and Illinois). See McCartin
McAuliffe Mechanical Contractor, Inc. v. Midwest Gas Storage,
Inc., 685 N.E. 2d 165, 173-74 (Ind. 1st Dist. 1997).
The issue of tendering unconditional mechanics lien waivers
in advance of payment is highly technical. It certainly is
not a recommended practice for potential claimants in Wisconsin.
John S. Mrowiec is a partner
with Chicago-based Conway & Mrowiec, a construction and
public contracts law and litigation practice. He may be reached
at (312) 658-1100. For information, go to the firm's Web site
at www.cmcontractors.com.
|