|
Consequential Damages of Contractor's Lost Future Profits
by John S. Mrowiec
Contractors or subcontractors frequently claim damages as
the result of delay or disruption for the costs of acceleration,
extended site overhead expenses or labor productivity impacts.
These damages arise directly from a breach of the underlying
contract or subcontract.
Sometimes, the claimant raises claims for damages which are
not as customarily claimed and do not arise in every situation.
For instance, a contractor might be required to move substantial
forces, supervision and even management from other projects
to the delayed project.
This might result in lost or reduced profits on those other
projects. Unabsorbed home office overhead, loss of bonding
capacity and lost profits of a going concern are other claims
that might occasionally arise. These nondirect damages are
often called "consequential" damages. Owners, too,
raise delay damages claims, some of which are considered "direct"
and some "consequential."
A Key Distinction
Contract law makes an important distinction between "direct"
damages and "consequential" damages. Sometimes,
the difference between the two is said to be the degree to
which the damages are a "foreseeable" or "highly
probable" outcome of a breach of the contract in question.
See Rexnord
Corp. v. DeWolff Boberg & Associates, 286 F.3d
1001, 1004 (7th Cir. 2002).
It is generally understood in the law that "consequential"
damages are more difficult to recover than are "direct"
damages. Most modern courts follow the approach that consequential
damages are recoverable only if they were foreseeable by the
breaching party (even if not actually foreseen) at the time
the contract was entered.
That principle originates in the English case of Hadley
v. Baxendale, 156 Eng. Rep.
145, 151 (1854). In Hadley,
the court held that a mill could not recover lost profits
from its carrier resulting from the carrier's delay in delivering
a mill part essential to operation of the mill. The Hadley
court found it was not reasonably foreseeable at the time
of entry of the carriage contract for the carrier to have
anticipated that delayed delivery of a single machine part
would cause the mill to shut down and lose profits.
The threat, if not the recovery, of consequential damages
claims is apparently of concern to construction project participants.
Indeed, the American Institute of Architects included a mutual
waiver of the owner's and contractor's claims for consequential
damages in its 1997 edition of the A201 General Conditions
of the Contract for Construction 4.3.10. For contracts without
such a mutual waiver, consequential damages still may be claimed
and, if the correct proof is presented, might be awarded.
Case Illustrates Issue
The recent case of Trenhaile
v. J.H. Findorff & Son, Inc., 2004 Wis. App.
LEXIS 384 (May 4, 2004), involved a subcontractor's claim
for consequential damages.
Trenhaile, doing business as Trenko Electric Inc., was an
electrical subcontractor on the reconstruction and rehabilitation
of two parts of the Jones Island Waste Water Treatment Plant
owned by the Milwaukee Metropolitan Sewerage District. Findorff
was the general contractor on both projects.
After completing approximately 90 percent of its work, the
subcontractor sold its assets to another electrical contractor
but continued to work on the projects under the direction
of the new ownership. When creditors, unrelated to the projects,
initiated an involuntary bankruptcy petition against the subcontractor,
it stopped the subcontract work on the projects. The general
contractor hired a replacement electrical subcontractor to
complete the projects.
The original subcontractor sued the general contractor seeking
payment of unpaid extras. In addition, the subcontractor contended
the general contractor caused the bankruptcy by failing to
pay the subcontractor's extras promptly. The subcontractor
sought damages for the "lost going concern value"
of the subcontractor.
The Trenhaile
case has a long history in the trial and appellate courts.
Ultimately, however, the trial court found, and the appellate
court affirmed the finding, that the general contractor delayed
or failed to pay amounts due to the subcontractor of $129,597
in receivables, causing the bankruptcy.
At one time the trial court also awarded the subcontractor
$558,532 for consequential damages for the subcontractor's
lost "going concern value." On the general contractor's
appeal, the appellate court initially reversed that consequential
damages award because the trial court had not made the necessary
findings.
After reconsidering the case, the trial court held that the
subcontractor was not entitled to recover lost future profits
or the lost future value of the company. The trial court reasoned
that the subcontractor had not proved that these damages were
reasonably foreseeable.
Case Appealed
The subcontractor appealed. On appeal, the Trenhaile
appellate court stated the rule of consequential damages in
Wisconsin: consequential damages may be awarded for a breach
of contract if such damages are reasonably foreseeable at
the time the contract was made, Trenhaile,
2004 Wis. App. LEXIS 384 at *11 citing Reiman
Associates, Inc. v. R/A Advertising, Inc., 306
N.W.2d 292, 300-01 (Ct. App. 1981).
The Trenhaile trial court's findings included that the general
contractor was unaware that "a delay in paying for extra
work and change orders would bankrupt" the subcontractor,
Trenhaile, 2004 Wis. App. LEXIS 384 at
*12. The appellate court reviewed the evidence and determined
that the trial court's findings were not "clearly erroneous,"
the standard for reversal of a trial court's factual findings.
The Trenhaile
decision can be contrasted with an earlier Wisconsin
case, Downey, Inc. v. Bradley Center Corp., 188
Wis.2d 435, 524 N.W.2d 915 (1994).
In Downey,
the mechanical subcontractor recovered a jury verdict for
direct damages for acceleration of an arena project where
the general contractor refused to grant time extensions for
delays caused by "holds" and by other subcontractors.
The subcontractor also recovered the additional consequential
damages of lost profits from independent contracts because
of the need to move forces, supervision and management to
the arena project.
The general contractor appealed in the Downey matter, claiming
the lost profits on other contracts were not reasonably foreseeable.
Applying Indiana law, the Downey
appellate court held that the subcontractor had proved that
the lost profits on independent contracts were reasonably
foreseeable.
The evidence showed that the general contractor had reason
to foresee that if it did not grant time extensions for the
numerous "holds" on the subcontractor's work and
instead told the subcontractor to "do whatever it had
to do," that the subcontractor would pull resources from
other projects and that those other projects could suffer,
Downey, 524 N.W.2d at 921, citing Insul-Mark
Midwest, Inc. v. Modern Materials, Inc., 594 N.E.2d
459, 467 (Ind. Ct. App. 1992).
The rule in Illinois is similar; consequential damages will
be awarded for breach of contract, in addition to direct damages,
if the claimant proves those consequential damages are "the
consequence of special or unusual circumstances which were
in the reasonable contemplation of the parties when making
the contract," Cencula
v. Keller, 180 Ill. App. 3d 645, 650, 536 N.E.2d
93 (2d Dist. 1989).
John S. Mrowiec is a partner
with Chicago-based Conway & Mrowiec, a construction and
public contracts law and litigation practice. He may be reached
at (312) 658-1100. For information, go to the firm's Web site
at www.cmcontractors.com.
|