|
Failing to Sign Subcontract Before Accident:
Prime Contractor Might Not Be 'Additional Insured'
by John S. Mrowiec
Some contractors and subcontractors have longstanding relationships.
Under such circumstances, the subcontractor might start work
before signing the contractor's standard written subcontract.
The contractor also might neglect to collect an insurance
certificate from the subcontractor naming the contractor as
an additional insured under the subcontractor's insurance
policy before allowing the subcontractor to begin work.
Suppose a subcontractor's employee is injured before a subcontract
is signed or an insurance certificate listing the contractor
as additional insured is tendered. Under such a situation,
will the contractor be an additional insured under the subcontractor's
comprehensive general liability policy if the subcontract
is signed later?
Indiana Case Touches Issue
The question was addressed in a recent Indiana case, Liberty
Insurance Corp. v. Ferguson Steel Company, Inc., 2004 Ind.
App. LEXIS 1461 (2d Dist., July 27, 2004).
Some time prior to Jan. 6, 2000, Steel Frame Erectors Inc.,
who was to be a subcontractor to the general contractor,
began work. On Jan. 6, 2000, one of the subcontractor's
employees was injured.
At the time of the injury, the subcontractor had a comprehensive
general liability insurance policy, and the insurer was
Liberty Mutual.
The policy contained an "Additional Insured Endorsement
Clause." The clause defined an additional insured as
the following:
"any person or organization for whom you are performing
operations when you and such person or organization have
agreed in writing in a contract or agreement that such person
or organization be added as an additional insured on your
policy [but] . . . only with respect to liability arising
out of your ongoing operations performed for that insured
. . . [until] your operations for that insured are completed."
A week after the injury, the general contractor, Ferguson
Steel Co., forwarded a subcontract to the subcontractor.
The subcontractor, and then the general contractor, signed
the written subcontract.
The subcontractor and general contractor had worked together
frequently. The subcontractor often began work with this
particular general contractor before signing a subcontract.
The subcontractor and general contractor had the understanding
that the subcontract would be in effect from the day work
commenced, even though signed thereafter.
The contractor did not have such an understanding with
other subcontractors. Instead, the general contractor required
a signed subcontract before permitting those subcontractors
to begin work.
The injured worker filed suit against the general contractor
and others. The general contractor tendered defense of the
worker's suit to the subcontractor's insurer. The subcontractor's
insurer refused to defend or indemnify the general contractor.
The general contractor sued seeking a declaration that the
insurer owed coverage.
Motions Filed
The general contractor and the subcontractor's insurer
each filed cross-motions for summary judgment. The trial
court held that the subcontractor's insurer owed coverage
to the general contractor. The insurer appealed.
The insurer contended that the unambiguous language of
the policy required that the subcontractor's agreement to
perform work had to be in writing to make the general contractor
an additional insured under the policy. Until there was
such a written agreement, the insurer argued, the general
contractor was not an additional insured. The injury occurred
prior to the signing of the written agreement.
The general contractor argued that it and the subcontractor
had an oral agreement before inception of the work, and
thus, before the injury, that would be, and in fact was,
later reduced to writing. Therefore, according to the general
contractor, the "in writing" requirement of the
insurance policy was satisfied and coverage should have
applied from the time the subcontractor began work which
is what contractor and subcontractor intended.
The Ferguson Steel appellate court began its analysis with
the legal principle that "when one enters into an agreement
with the understanding that neither party is bound until
a subsequent formal written document is executed, no enforceable
contract exists until the subsequent document is executed,"
Ferguson Steel, 2004 Ind. App. LEXIS 1461, *6 citing Wolvos
v. Meyer, 668 N.E.2d 671, 675 (Ind. 1996). The subcontract
contained an integration clause: The subcontract provided
it was "the entire and integrated agreement between
the parties hereto and superseded all prior negotiations,
representations, and agreement, either written or oral."
The appellate court concluded that there was no effective
written agreement until the subcontract was signed, too
late for coverage for this injury.
The appellate court ruled that the insurer was required
to insure the general contractor only based upon the written
agreement and not on the intentions of the general contractor
and subcontractor to be bound to a subsequently signed writing.
There was no evidence that the insurer had knowledge of
the contractor-subcontractor understanding.
After all, the court reasoned, the insurer could not be
expected to insure a party without knowledge of the name
of the party, the period of coverage or of the insurer's
obligation to do so. (But the court did not explain whether
the policy even required the subcontractor to provide the
writing to the insurer as a condition to insuring a general
contractor.)
The general contractor argued that it had a "course
of dealing" with the subcontractor that signing a writing
merely formalized a pre-existing agreement. The Ferguson
Steel court noted that a course of dealing is an established
pattern of conduct between the parties to a particular transaction.
But the insurer was not a party to the subcontractor-general
contractor agreement; the insurer was a party to a separate
agreement with the subcontractor that required a written
agreement before the insurer would be obligated to insure
a general contractor.
Nor would it matter to the Ferguson Steel appellate court
whether there was a customary practice in the construction
industry to delay written agreements until after work commenced.
This general contractor generally did not allow work commencement
without signing a written subcontract except with this subcontractor.
Appellate Court Reverses Decision
The Ferguson Steel appellate court reversed the trial court
and held the insurer owed no coverage to the general contractor.
Therefore, no matter how much trust two parties have for
each other, commencing work without a written subcontract
might leave the general contractor to rely on its own insurance
to defend suits from injured subcontractor employees for
incidents occurring before the subcontract is signed or
no certificate is collected.
Sometimes a contract will provide an "effective as
of" date, such as the date of work commencement, even
though it was signed later. Neither the facts nor analysis
of Ferguson Steel address whether the subcontract used an
earlier "effective date." Thus, we do not know
whether that common practice would have changed the Ferguson
Steel result under the language of the particular insurance
policy.
John S. Mrowiec is a partner
with Chicago-based Conway & Mrowiec, a construction
and public contracts law and litigation practice. He may
be reached at (312) 658-1100. For information, go to the
firm's Web site at www.cmcontractors.com.
|