| Contractors'
Right to Assert Subcontractors' Claims Recognized By
John S. Mrowiec
A common project pattern involves an owner-caused
delay, owner's architect's errors or omissions or disputed extras. The event might
have caused little or no damages to a prime contractor but caused substantial
damages to one or more subcontractors.
Normally, because the subcontractor
is not "in privity" with the owner, the subcontractor cannot sue the
owner for the subcontractor's damages. The subcontractor may sue the prime contractor.
The prime contractor then will want to sue the owner so as to recover from the
owner any amount the contractor is ordered to pay the subcontractor.
The
industry typically refers to a claim where the prime contractor sues the owner
to recover the subcontractor's damages as a "pass-through claim."
Both
federal and state courts have recognized a prime contractor's legal right to assert
a subcontractor's pass-through claim against an owner under most circumstances.
Often the prime contractor and subcontractor sign a "claims prosecution"
or "liquidating" agreement providing for how the claim will be prosecuted
and how the subcontractor will be paid.
View from
Texas Recently, a federal court that was obligated to apply unclear Texas
law asked the Texas Supreme Court whether Texas law recognized pass-through claims
against an owner when there was no privity of contract between the subcontractor
and the owner. After surveying case decisions regarding federal contracts and
state public and private contracts that had considered the question, Texas joined
in the majority of courts that allow pass-through claims, Interstate Contracting
Corp. v. City of Dallas, 135 S.W. 3d 605 (Tex. Apr. 16, 2004), reh'g denied, 2004
Tex. LEXIS 354 (Jun. 25, 2004).
The Interstate Contracting court concluded
that federal courts addressing federal contracts have held that as long as the
prime contractor remains liable to the subcontractor for the subcontractor's damages,
the prime contractor may bring an action against the owner for the subcontractor's
damages, Interstate Contracting, 135 S.W. 3d at 611. The reasoning is that "[the
contractor] was the only person bound to perform his contract with the Government,
and he had the undoubted right to recover from the Government [extra costs and
services] whether that work was performed personally or through another"
Interstate Contracting, 135 S.W. 3d at 610 quoting United States v. Blair, 321
U.S. 730, 737-38 (1944). In the federal contracts context, the prime contractor
originally could not pass-through a subcontractor's claim if the subcontract contained
language constituting a "complete release" of the prime contractor.
Severin v. United States, 99 Ct. Cl. 435, 443 (1943).
However, that "Severin
doctrine" has been "narrowly construed" and "diluted"
by subsequent cases that have "interpret[ed] releases and contracts generously
to let contractors pursue their subcontractor's claims" Interstate Contracting,
135 S.W. 2d at 612 citing E.R. Mitchell Construction Co. v. Danzig, 175 F.3d 1369,
1371 (Fed. Cir. 1999); Morrison-Knudsen Corp. v. Firemen's Fund Ins. Co., 175
F.3d 1221, 1251 (10th Cir. 1999).
The Interstate Contracting court noted
that 19 states, by state court or federal court decisions applying state law (some
in multiple cases), had addressed the concept of pass-through claims. Eighteen
states had recognized the validity of such claims and only Connecticut had not,
Interstate Contracting, 135 S.W. 3d at 613-14. The Interstate Contracting case
added Texas to the states recognizing the pass-through claim concept, Interstate
Contracting, 135 S.W. 3d at 618.
Illinois Case Remarkably, apparently none of the state appellate courts
in or federal courts applying the law of our readership's area of Illinois, Indiana
or Wisconsin had squarely addressed the issue of the validity of pass-through
claims as of the time of the Interstate Contracting decision. Then, just months
later, an Illinois court addressed the question in Paschen Contractors, Inc. v.
City of Kankakee, 2004 Ill.App. LEXIS 1403 (3d Dist., Nov. 22, 2004).
In
Paschen Contractors, a prime contractor sued a public owner asserting the prime
contractor's own damages and those of an electrical subcontractor. The subcontract
provided that the prime contractor would not be liable to the subcontractor for
extras until the prime contractor had been paid by the owner.
The owner
denied five of the prime contractor's change order requests totaling $1,940,130.
"The net-effect of the denial" was that the prime contractor failed
to pay the subcontractor approximately $1.6 million, Paschen Contractors, 2004
Ill.App. LEXIS 1403 at *5.
The prime contractor entered into a written
"settlement agreement" with the subcontractor under which prime contractor
paid the subcontractor $100,000 and they agreed to cooperate and prosecuted a
"Consolidated Claim," Paschen Contractors, 2004 Ill.App. LEXIS 1403
at *5-6.
Although the procedural history of the case is lengthy and complex,
the prime contractor ultimately sued the public owner to recover the consolidated
claim.
Eight paragraphs of the prime contractor's pleading expressly raised
the subcontractor's pass-through claims.
The owner moved to strike those
allegations "citing the well-established rule that subcontractors may not
recover against the land owner in the absence of a contractual relationship"
Paschen Contractors, 2004 Ill.App. LEXIS 1403 at *6. The trial court agreed and
struck the prime contractor's allegations seeking to recover for the pass-through
claims. As part of an appeal addressing many issues, the appellate court
reversed the trial court's holding that the prime contractor could not assert
the pass-through claims. The Paschen Contractors court agreed with the reasoning
of the Blair decision: "[the owner] required [the prime contractor] to perform
extra work beyond the terms of the contract. That [the prime contractor] subsequently
engaged [the subcontractor] to perform some of that work is irrelevant. [The prime
contractor] has the right to recover" Paschen Contractors, 2004 Ill.App.
LEXIS 1403 at *19.
Therefore, Illinois has joined Texas, the federal contracting
decisions and 18 other states in expressly recognizing the pass-through concept. John S. Mrowiec is a partner
with Chicago-based Conway & Mrowiec, a construction
and public contracts law and litigation practice. He may
be reached at (312) 658-1100. For information, go to the
firm's Web site at www.cmcontractors.com. |