| Quantifying
the Impact of Change Orders By
John S. Mrowiec
Contractors or subcontractors sometimes
seek compensation for labor cost overruns, contending that project change has
adversely affected their labor productivity on the unchanged work.
Among
typical owner responses are that the claimant has demonstrated no link between
the change and labor productivity on other work, the claimant has not ruled out
other causes, signed change orders release that "cumulative impact"
claim or the amount sought is overstated. Owners and the courts seek evidence
for causation of change to reduced labor productivity.
Contractors have
sought empirical support for the concept that change might adversely impact unchanged
work on a particular project.
Beyond that, there seems to be no method
to recognize this phenomenon, much less to quantify it, at the time of agreeing
to specific change orders.
Previous Studies
Done In the March 2003 issue, we wrote about some of the empirical studies
of the effect of project change orders on labor productivity. One of the more
prolific authors of some of the most recent studies was Professor Awad Hanna of
the University of Wisconsin at Madison.
Between 1999 and 2002, he had teamed
with others to publish three studies: A. Hanna, J. Russell, T. Gotzion & E.
Nordheim, Impact of Change Orders on Labor Efficiency for Mechanical Construction,
125 J. Constr. Eng. & Mgmnt. 176 (1999); A. Hanna, J. Russell, E. Nordheim
& M. Bruggink, Impact of Change Orders on Labor Efficiency for Electrical
Construction, 125 J. Constr. Eng. & Mgmnt. 224 (1999); and A. Hanna, R. Camlic,
P. Peterson & E. Nordheim, Quantitative Definition of Projects Impacted by
Change Orders, 128 J. Constr. Eng. & Mgmnt. 57 (2002).
Summarizing
the 1999 studies, the authors reported that there appeared to be a relationship
between the timing of change orders and the amount by which labor efficiency was
impacted. Those 1999 studies reported a "direct relationship" between
change orders and schedule compression, stacking of trades and the sequencing
of work.
Quantifying Change Order Effect Unanswered by the 1999 and 2002 studies
was, even if it is more likely than not that the cumulative impact of the change
orders were the cause of reduced labor productivity, how does one quantify the
impact caused by the change orders?
A new study attempts to answer that
question, A. Hanna, R. Camlic, P. Peterson, M. Lee, Cumulative Effect of Project
Changes for Electrical and Mechanical Construction, 130 J. Constr. Eng. &
Mgmnt. 762 (Dec. 2004).
The study reviewed electrical and mechanical projects
with lump-sum contracts, employing a design-bid-build project delivery system
and between 2,000 and 240,000 manhours in size. Labor hours were used as the basis
of defining percentage of change, productivity loss and project size. That way,
geographic price differences are eliminated.
According to the authors,
a delta approach can show both cause and effect of the cumulative impact of the
change order.
Delta was defined as the difference between the actual labor
hours to complete the project and the estimated base hours plus the approved change
order hours. Positive deltas reflect a loss, and negative deltas a higher-than-expected
efficiency.
The authors note that delta can result not only from change
orders but from contractor-caused inefficiencies, underestimated original contract
hours or other productivity inhibitors like weather.
Data was collected
in conjunction with the Construction Industry Institute. The 2004 study included
only those projects where it had been determined that change orders were the "main
reason" for productivity loss and where the contractors believed the original
estimates were reasonable.
Then, the authors employed a two-phase approach.
First,
the authors performed statistical hypothesis testing on 70 variables to determine
correlation between those factors and the percent delta. Second, the authors employed
the multiple linear regression process to develop a model from the independent
variables in the database that would predict the value of the dependent variable,
percent delta.
Some factors were found to be significant in the first phase
hypothesis testing but were eliminated in the second phase because they were found
not to have predictive power when interacting with other factors. The study then
involved a sensitivity analysis of the regression model to determine if the variables
in the model affect the final value of percent delta.
Study Results The study found that the percent delta increased (more non-change
order labor overrun) as the percent of change increased and as change order processing
time increased.
However, when contractors regularly track labor productivity,
the percent delta is significantly lower (less non-change order labor overrun)
than when productivity is not tracked.
The variables ultimately judged,
in combination, as most reliable for predicting the quantity of impacted labor
hours and their determined coefficients were (1) percentage of project change
(0.12), (2) percentage of project manager time devoted to the project, (-0.08),
(3) percentage of owner-initiated (as opposed to design errors) change (-0.17),
(4) whether the contractor tracked productivity (-0.09), (5) whether there was
over manning (-0.05), and (6) change order processing time (0.02).
The
study tested its predicting model on 42 projects with 78 percent predicting the
labor overrun within 10 percent of the actual loss, and then used seven new projects
to validate the model. All seven predicted the loss within 16 percent of the actual.
Whether
the 2004 study actually will be employed by claimants, and accepted by courts,
for quantifying the cumulative impact of changes on the unchanged work, remains
to be seen. The study did result in some claims prevention advice to owners and
contractors.
The authors recommend that owners attempt to limit changes
from design errors by spending more time and money with the design team ahead
of construction. When changes arise, reduce the processing time.
They also
recommend that contractors spend more effort in tracking productivity during the
project. They find that projects where the contractor updates the schedule regularly
had lower productivity losses. John S. Mrowiec is a partner
with Chicago-based Conway & Mrowiec, a construction
and public contracts law and litigation practice. He may
be reached at (312) 658-1100. For information, go to the
firm's Web site at www.cmcontractors.com. |