| The Contract
and Assessing Performance By John
S. Mrowiec
Performance criteria often dictate a standard
for a portion of a construction project.
For example, specifications might
require a "leak-free" curtain wall system.
Sometimes whether
a system will meet the performance criteria depends on what type of test is applied.
Some tests are easier to pass than others.
Often, the specification will
set forth the test that the system must pass. Sometimes, subcontractors or suppliers
will provide a clarification that the system installed will be tested under a
particular method. The prime contractor might agree to include that clarification
as part of the subcontract.
Does a specified testing method always govern?
Does express inclusion of the subcontractor's requested testing method into the
subcontract mean that the subcontractor's method will be the one applied?
Neither
might govern necessarily as seen by the decision in Clark Construction Group,
Inc. v. Allglass Systems, Inc., 2004 U.S. Dist. LEXIS 15459 (D. Md. 2004).
Curtain Wall System Dispute Allglass Systems involved a
dispute about defective performance of a curtain wall system and resulting construction
delays while the system was remediated.
Clark Construction was the general
contractor for construction of an office building in Washington, D.C., and Allglass
Systems was a subcontractor that agreed to install windows and related panels,
glazed curtain wall, aluminum curtain wall and caulking and sealing.
The
subcontractor hired a fabricator for the curtain wall, Kawneer Company Inc., but
the subcontractor installed the curtain wall and the caulking and sealant.
The
"Performance Criteria" of the subcontract required the curtain wall
subcontractor to "design, fabricate, and install each type of curtain wall,
including joints between window walls and other work to effectively prevent leakage
of either water or air into the building."
The specifications provided
that the curtain wall system was to pass "a hose test." The Subcontract
required that the subcontractor install its window system within 20 weeks of its
work commencement.
Tests Show Flaws After installation, there were a series
of tests conducted by various consultants for parties that included the fabricator,
the subcontractor and the owner's representative.
Each concluded that
the installation was flawed, including the subcontractor's consultant.
The
subcontractor began remediation. Even after the partial remediation, portions
of the system continued to leak.
The contractor hired another subcontractor
to supplement the remediation effort. The remediation was not successfully completed
until 11 months after the subcontractor originally was to have been complete and
ultimate completion was through a supplemental subcontractor.
The subcontractor's
own internal documents admitted that the tests revealed "lack of proper sealant"
in "many" locations. To finance the remediation effort, the subcontractor
chose not to pay its sub-subcontractors and suppliers.
Suits Filed The prime contractor sued the subcontractor and the subcontractor's
surety. The prime contractor sought damages for (1) costs to complete and to correct
the subcontractor's work through the hiring of the supplemental subcontractor;
(2), payments to the subcontractor's subcontractors and suppliers; (3) increased
general conditions costs because of additional supervision and time-related costs;
(4) supplement with the owner for owner's costs and delays; and (5) attorneys'
fees.
The subcontractor denied liability and counterclaimed for withheld
subcontract balances. The prime contractor and subcontractor each moved for summary
judgment.
The subcontractor made a number of arguments, and for the purposes
of this article, we will focus on one.
The subcontractor did not challenge
the substantive findings of the various reports.
Rather, the subcontractor
argued that the windows leaked because the prime contractor performed a "more
stringent" "chamber test" than the "hose test" that was
referenced in the specifications. According to the subcontractor, use of the "chamber
test" was a "constructive change."
It is unclear whether,
in light of the numerous deficiencies found, the windows would have flunked a
"hose test" as well. Regardless, the Allglass Systems court noted that
the subcontractor's reliance on the "hose test" reference overlooked
an important contractual provision.
The subcontract expressly incorporated
the Owner-Contractor Agreement. That Agreement expressly incorporated the American
Institute of Architects, General Conditions of the Contract for Construction.
The
General Conditions, section 13.5.2 provided that if the owner determines that
"portions of the Work require additional testing, inspection or approval
[beyond that 'required by the Contract Documents'] . . . the [Owner] will . .
. instruct the Contractor to make arrangements for such additional testing, inspection
or approval" Allglass Systems, 2004 U.S. Dist. LEXIS 15459, *17. (The General
Conditions section 13.5.2 cited in Allglass Systems matches the AIA A201 General
Conditions, section 13.5.2 (1997 ed.)).
This "additional testing"
was owner's right, the court held, and by incorporation by reference, bound the
subcontractor. Although not discussed by the Allglass Systems court, the General
Conditions go on to say that the owner will bear the cost if the work passes the
additional test, but if the work fails, contractor (and subcontractor, by incorporation)
bear all costs.
The court granted summary judgment on liability for the
contractor against the subcontractor's performance bond surety. The only issue
left for trial on the contractor's complaint was the amount of damages.
The
Allglass Systems case shows that the specified testing method might not apply
if the Owner exercises its rights under an "additional testing" provision
worded like that of the AIA A201 General Conditions. An express exclusion of that
"additional testing" right in the Owner-Contractor Agreement or in the
subcontract might dictate a contrary result. John
S. Mrowiec is a partner with Chicago-based Conway & Mrowiec, a construction
and public contracts law and litigation practice. He may be reached at (312) 658-1100.
For information, go to the firm's Web site at www.cmcontractors.com. |