News
 Association
 Law/Courtroom
 Building
 Design
 Infrastructure
 Personnel
 Illinois
 Indiana
 Wisconsin
 Submit News





Construction Law - October 2005

Overtime, Project Size and Labor Productivity


By John S. Mrowiec


In the February 2001 issue of Midwest Construction, we discussed some of the empirical research which attempted to quantify reduced labor productivity resulting from working overtime hours as compared to productivity for labor hours where overtime was not utilized.

Owners, contractors and subcontractors often dispute the amount of proper compensation for overtime.

Aside from disputing the reasons for the need for overtime, the parties dispute how much the compensation for the overtime should be. Is it merely the premium time wage and burden differential on the overtime hours or, instead, that amount plus some multiplier of the total hours worked for "loss of productivity" caused by working overtime?

Professor Awad Hanna, who has written a number of articles on construction labor productivity, along with other contributors, has recently published a new article. Hanna explores the "quantitative relationship among overtime, project duration, and labor productivity on projects employing extended-duration overtime," A. Hanna, C. Taylor and K. Sullivan, Impact of Extended Overtime on Construction Labor Productivity, 131:6 J. Constr. Eng. & Mgmn't 734 (June 2005).


Research Aim

The objective of Hanna's research was to attempt to quantify the impact on labor productivity of employing overtime for long durations.

Typically, we think of the use of overtime as necessary to overcome project delays. Increasingly, however, overtime is planned from the inception.

Planned overtime is used to address craft labor shortages by providing incentive to the craft laborers of the certainty of premium pay or because the owner wants the completed project as fast as possible for market reasons.

Overtime is often preferred as a schedule compression technique over the use of shift work (which presents coordination difficulties) or additional manning (which depends on availability and its own set of productivity issues.)

Nevertheless, overtime might introduce a series of problems including fatigue, low morale, a higher cost per unit, a higher accident rate and, as described by the U.S. Army Corps of Engineers in 1979, a pacing phenomenon, any or all of which might lead to reduced labor productivity and increased costs. Disputes about payment for this lost productivity lead to expensive legal battles.

Previous overtime studies, according to Hanna, focused on overtime solely as a short-term schedule compression technique. Accordingly, Hanna contends these studies can be applied properly only to projects with no more than 15 continuous weeks of overtime.

Hanna also cites the critiques of earlier overtime productivity research. One author argued that the overtime data published by Kosarris (1947), National Electrical Contractors Association (1969), the Mechanical Contractors Association of America (1976), U.S. Army Corps of Engineers (1979) and Business Roundtable (1980) might be taken from one or two common sources and then manipulated to make each study appear unique, R.E. Larew, Are Any Construction Overtime "Studies" Reliable? 40:9 Cost. Eng. 24 (1998).

Data Collected

Hanna collected his data by a questionnaire directed primarily to union specialty electrical, mechanical and general contractors performing labor intensive work across the United States. Data collected included project type, specific trade work, budgeted and actual hours expended, estimated and actual project duration, average hours worked per crewmember per week, crew schedule used, crew size and union or non-union workforce.

Eventually the project databank contained 88 projects: 30 using a 5(10)s schedule, 13 using a 6(10)s, 23 using a 5(8)s and 22 using a 4(10)s schedule. The projects ranged in size from 700 to over 1.4 million work-hours. Hanna opined that this large diversity contained within the data set allows the final regression model to be applicable to a wide spectrum of projects.

Hanna then employed both hypothesis testing and regression analysis. The hypotheses testing supported findings from earlier studies that the 5(10)s and 6(10)s schedules were shown to significantly reduce levels of productivity, on average, compared to the two 40 week schedules. The hypothesis testing showed there was no significant productivity difference between the 5(8)s and 4(10)s schedules.

However, the 6(10)s was significantly less productive than the 5(10)s schedule.

To arrive at a quantitative relationship among productivity, overtime and project size (measured by total work hours), Hanna used regression techniques. He was able to develop a series of tables suitable for predictive use in the seven 200,000 man-hour increments from 700 to 1.414 million hours. Because the regression model was developed with projects using a single crew schedule, Hanna cautions that the model cannot be used to predict productivity on a combination of schedules.

Research Results

Hanna's results are shown in the article for actual work hours between 200,000 and 400,000 and for weekly average hours ranging from 32 to 65. He cautions that the results should be applied only to projects with those parameters. (Results from greater hourly project sizes are available from the Construction Industry Institute.)
In general, Hanna's results at the project size of 200,000 to 400,000 man-hours showed productivity was reduced between 4 percent and 5 percent for each 5-hour additional increment above 35 hours. Average productivity for projects employing a 60-hour work-week was 24 percent less than for a 40-hour workweek at a 200,000 hour project size and 23 percent less at a 400,000 hour project size.

Employing a 50-hour workweek, the productivity was 8 percent less than for a 40-hour workweek at a 200,000-hour project size and 9 percent less at a 400,000-hour project size. Hanna's article should be consulted for more precise results in comparing project size to weekly hours.

Comparing to earlier overtime studies, Hanna's 2005 study was developed from current project data in a database of 88 projects. Additionally, none of the earlier studies analyzed the impact of extended overtime and, thus, they were to be limited to projects using overtime for less than 15 weeks.

Hanna argues his model thus is superior to older studies. He asserts his results may be used proactively to estimate planned overtime and reactively in a claim setting.

The time for critique of the Hanna study has not yet elapsed. Depending on whether any critique is valid, the Hanna 2005 study might become the new benchmark for measuring the impact of overtime on labor productivity for most construction projects.

A Postscript from Wisconsin

Our January 2004 article in Midwest Construction was entitled May a Mistaken Public Bid be Withdrawn Without Penalty?

A featured case in the article was the Wisconsin Appellate Court's Opinion in James Cape & Sons Co. v. Mulcahy, 268 Wis. 2d 203, 672 N.W. 2d 292 (4th Dist. 2003).

Recently, the Wisconsin Supreme Court affirmed the Appellate Court's holding. A contractor should have been allowed to withdraw its bid under Wisconsin Statute § 66.0901 (5) and have its bid bond returned.

The contractor had swiftly notified the public owner of a failure to incorporate a subcontractor's last minute change in offered subcontractor price into contractor's bid price. Under the facts of the case, it was not clearly erroneous for the trial court to have held that the contractor's mistake was free from carelessness, negligence and inexcusable neglect, James Cape & Sons Co. v. Mulcahy, 2005 Wis. LEXIS 392 (July 15, 2005).

John S. Mrowiec is a partner with Chicago-based Conway & Mrowiec, a construction and public contracts law and litigation practice. He may be reached at (312) 658-1100. For information, go to the firm's Web site at www.cmcontractors.com.

 


 Click here for more Construction Law News >>



advertisement


 


Sponsors

© 2009 The McGraw-Hill Companies, Inc.
All Rights Reserved