News
 Association
 Law/Courtroom
 Building
 Design
 Infrastructure
 Personnel
 Illinois
 Indiana
 Wisconsin
 Submit News





Construction Law - February 2006

Many RFIs Could be Insufficient To Recover Delay Damages


By John S. Mrowiec


Normally, this column focuses on case decisions from our readership's area of Illinois, Indiana, eastern Missouri and Wisconsin.

But we are straying from our usual geography this month to discuss an interesting case.

The United States Supreme Court long ago articulated the Spearin doctrine:

"If the contractor is bound to build according to the plans and specifications prepared by the owner, the contractor will not be responsible for the consequences of defects in the plans and specifications . . . This responsibility of the owner is not overcome by the usual clauses requiring builders to visit the site, to check the plans, and to inform themselves of the requirements of the work" United States v. Spearin, 248 U.S. 132, 136 (1918).

As we noted in the October 2000 column, breach of the implied warranty of the plans and specifications might result in a contractor recovering reasonable costs attributable to delay resulting from the defective design. (See Delays Arising from Defective Design: Not the Usual "Change".)


A New Case Arises

Nevertheless, a new case teaches that proof of numerous contractor requests for information might be insufficient to support a contractor's recovery of delay damages where the contractor fails to provide an identifiable design defect or set of design defects, Dugan & Meyers Construction Co. v. Ohio Dep't of Admin. Services, 162 Ohio App. 3d 491 (10th Dist., July 28, 2005).

The Dugan & Meyers Construction Co. case involved construction of phase two of the Ohio State University Fisher College of Business, which is comprised of three buildings. The lead contractor, Dugan & Meyers Construction Co., was required to coordinate the work of multiple prime contractors, including preparing and maintaining the project's schedule.

In addition, the lead contractor also was awarded the general trades prime contract which included the construction of the concrete and build-out of the three buildings.

Together, the contractor's price was nearly $21 million with $12 million in other prime contracts.

Except for a one-month "no cost" time extension because of unavailability of steel,
construction proceeded smoothly for the first year.

But between June and September 1998, 176 requests for information regarding the plans and specifications had been submitted, many resulting in field work orders. The architect issued a field work order where changes to the plans were required resulting in additional cost or time.

By February 1999, the lead contractor's schedules projected delays to the buildings' completion dates beyond the extended dates. In early April 1999, the owner, associate architect and owner's separate construction manager told the lead contractor that it was critical to complete one particular building and several floors of another by the extended contractual completion date for classes; if these could be completed timely, time extensions might be available for the balance of the areas.

But through June 1999, submission of RFIs and issuance of field work orders continued. Other than attributing four days of delay regarding one of the RFIs, the lead contractor never sought time extensions or delay compensation in writing.

Contractor Relieved of Duties

Finally, in late June 1999, the architect sent the lead contractor a default letter for "failure to prosecute the work so as to complete the work by the applicable milestones." Shortly thereafter, the owner's construction manager relieved the lead contractor of that role.

One of the buildings was completed on time by the construction manager so that classes could be held. The balance of the project was delayed approximately six months.

The owner assessed against the lead contractor both liquidated damages (after apportionment) and the cost of the construction manager to complete the lead contractor's role.

The lead contractor sued in the Ohio Court of Claims for breach of contract and, alternatively, for unjust enrichment. The owner counterclaimed for breach of contract seeking liquidated damages plus the cost paid to construction manager to complete lead contractor's performance.

A referee held a 17-day trial and issued a 74-page recommendation in favor of lead contractor for an award of $1,996,421 before interest. The award represented $1,192,585 in contract balance (reversing $589,840 of owner's backcharges) and $803,836 in "delay damages" or "cumulative impact damages." The referee denied lead contractor's claims for unabsorbed home office overhead and for lost profits (other than a 10 percent margin as part of the "cumulative impact" damages).

The trial court adopted the referee's decision with the exception of some minor items and awarded the lead contractor $752,623 in prejudgment interest. The owner appealed.

On appeal, the owner raised a number of defenses some based on contract language. The Dugan & Meyers Construction Co. appellate court found two of the owner's arguments sufficient to reverse the trial court's award in favor of the lead contractor. Accordingly, it was unnecessary to reach the owner's other contract-based arguments.

Appellate Court Reverses Decision

The appellate court reversed the award of "cumulative impact" damages reasoning that:

"In our view, the implied warranty of the plans and specifications identified in Spearin, is not appropriately invoked in the present case. The Court of Claims interpreted the so-called 'Spearin Doctrine' to stand for the proposition that [the owner] warranted the plans and specifications it furnished against any problem, need for clarification, minor deficiency, or subsequent deviation. Spearin does not stand for the proposition that owners, by virtue of having furnished the plans and specifications for the job, will indemnify and hold contractors harmless for all delays occasioned by agreed changes in the work necessitated by some force not within the complete control of the contractor.

"This is true even where, as here, the record reflects that the contractor issued a large number of RFIs (162 Ohio App.3d at 502)."

The appellate court recognized that it had itself applied the Spearin doctrine in an earlier case. Nevertheless, the Dugan & Meyers Construction Co. "decline[d] to permit the extension of the Spearin warranty in this case" 162 Ohio App. 3d at 503. Unlike the referee, who "was clearly persuaded to award delay damages because of the sheer numerosity of the RFIs", the appellate court found that the contractor was required to prove more (162 Ohio App. 3d at 503.)

Lacking in the contractor's proof, according to the appellate court, was any evidence "that the substantive concerns addressed in any one RFI or group of RFIs rendered the owner-furnished plans and unbuildable or otherwise wholly inadequate to accomplish the purpose of the contract" 162 Ohio App.3d at 503. Therefore, the contractor could not collect any delay damages resulting from design errors and omissions.

Not only could the lead contractor not collect its delay damages but the appellate court held that the owner could recover liquidated damages for delay (162 Ohio App.3d at 504). The lead contractor did not dispute that it failed to request extensions of time in writing as the contract required. Instead, the lead contractor argued that doing so should not be a prerequisite for defending against liquidated damages because owner would not have granted those requests anyway.

The evidentiary basis for the lead contractor's argument was that the owner had no alternative arrangements in place for holding many of the classes that the college had planned to conduct. That fact, according to the court, did not prove that the owner would have refused time extensions if they had been requested. Indeed, if lead contractor had requested time extensions, the appellate court remarked that extensions likely would have been appropriate (162 Ohio App.3d at 504-05).

(Contractors sometimes do not associate a time extension request with a particular RFI response where individually, the response might have little or no time impact.)

One of the members of the three-judge panel in Dugan & Meyers Construction Co. dissented. The ground of the dissent was that the referee, as the trier of fact, made appropriate factual findings including that the owner had failed to present evidence to refute the contractor's evidence of impact resulting from the numerous design changes.

The outcome of the Dugan & Meyers Construction Co. case cautions that contractors might need to prove the quality (not just the quantity) of design errors and omissions to prevail on a Spearin-type claim, if the contractor even chooses to so characterize it.

Certainly, prudent contractors should not ignore contractual requirements for the submission of written time extension requests if at all possible.


John S. Mrowiec is a partner with Chicago-based Conway & Mrowiec, a construction and public contracts law and litigation practice. He may be reached at (312) 658-1100. For information, go to the firm's Web site at www.cmcontractors.com.

 


 Click here for more Construction Law News >>



advertisement


 


Sponsors

© 2008 The McGraw-Hill Companies, Inc.
All Rights Reserved