News
 Association
 Law/Courtroom
 Building
 Design
 Infrastructure
 Personnel
 Illinois
 Indiana
 Wisconsin
 Submit News





Construction Law - April 2006

Perils of Remedying Disputed
Defective Design or Construction


By John S. Mrowiec


Determining the cause of water infiltration into a building can be challenging. Which elements of the structure are leaking? Is it a design, fabrication, installation or maintenance issue?

Initial impressions, even consensus opinion developed by experts years later, might later prove to be mistaken.

Litigation may be likely or, perhaps, already has commenced. How and how quickly can the infiltration be corrected? Does investigating or correcting the problem destroy the evidence necessary to determine causation and fault? What if an initial impression, or even consensus opinion, about the cause ultimately proves to be mistaken?

An owner recently learned an expensive lesson on the perils of attempting to correct water infiltration while litigation was ongoing in Harborview Office Center, LLC v. Camosy, Inc., 2006 Wis. App. LEXIS 149 (2d Dist. Feb. 15, 2006).

A developer, Harborview Office Center LLC, entered into a construction contract with Camosy Inc. as general contractor to construct a three-story office building in Kenosha.

The building envelope included aluminum windows and an exterior insulation and finishing system (EFIS). A component of the EFIS System is a plastic foam board insulation approximately 1 to 1.5 in. thick referred to as an expanded polystyrene layer (EPS).

For architectural interest there were 0.75-in.-deep horizontal and vertical V-shaped grooves cut into the EPS. A waterproof basecoat and embedded fiberglass mesh were then applied to the entire face of the EPS board over the V-grooves before application of a stucco-like finish coat over the basecoat.


Water Problems Start

The project was completed in late 1997. In late 1997 or early 1998, prior to tenant occupancy, signs of water infiltration appeared. The owner discovered additional water leaks with each rainstorm.

The contractor, architect, window installer and EFIS installer participated in varying degrees in early efforts to identify the cause of the leaking and to remedy the problem.

The efforts were only partially successful in reducing water infiltration.

Approximately four years after project completion, the owner sued the contractor, the architect, the window installation subcontractor and the EFIS installation subcontractor. The owner's complaint, and subsequent pleadings, each alleged "significant and recurring water infiltration" and continued that "[w]ith nearly every rain, windows leak." The owner contended that it would be necessary to remove and replace all of the windows to resolve water infiltration problems.

At some point, one of the owner's insurers, paid under an insurance policy, but the court opinion does not disclose the amount. The insurer intervened in the case.

The parties retained experts to identify the design and construction deficiencies causing the water infiltration and to evaluate a process to correct deficiencies. The owner's expert opined on several deficiencies that contributed to the water infiltration.

He did not consider that cracks in the V-grooves of the EPS portion of the EFIS System were a cause.

Remediation Starts

By May 2003, the owner wanted to proceed with remediation. On May 28, 2003, the owner conducted a demonstration on how EFIS would be removed around windows, removal of the windows and inspection of head jambs and sill flashing. The parties, some of the experts and counsel were in attendance. The owner's expert would supervise the remediation.

The owner hired a contractor to perform the remediation. When the remediation contractor visited the site to measure the windows, he noticed cracks in the V-grooves.

Concerned that window replacement would not completely resolve the leaks, the remediation contractor suggested that water testing be performed.

The owner told the remediation contractor that there had been enough testing and wanted to proceed with remediation. According to the owner, the cracks were "superficial" and an EFIS installer and expert had analyzed them.

After the new windows were installed, the owner's expert conducted water tests. When an area failed, it was determined that there was a "slight leak through a crack" in the EFIS.

Now, the owner's expert suspected that cracks in the V-grooves were a potential source of water infiltration. The next test area failed too.

Given the results of the water tests on the first two areas, the owner's expert advised owner that defects in the V-grooves were a possible source of water infiltration. The owner's expert ordered the remediation contractor to grind and refinish the V-grooves.

After grinding and refinishing the V-grooves, the water test passed. Thereafter, all V-grooves were ground and refinished. By Sept. 18, 2003, the reworking of the V-grooves was substantially complete. The owner's expert did not tell the other parties about his new opinion or of the V-groove work.

Spoiled Evidence?

On Sept. 17 and 18, 2003, the principals of the owner testified at deposition that their expert had recommended the repair of EFIS cracks, that the cracks were a source of water infiltration and that they had authorized repair work beyond the original window replacement.

After additional discovery, the various defendants filed a motion to dismiss the case on the ground that the owner had spoiled the evidence. The trial court found that the first time defendants had noticed that the owner contended the V-grooves were a source of water infiltration was at the owner's principals' depositions after the V-grooves already had been ground.

The trial court dismissed the case. The owners performing the V-groove work, defendants' "ability to gather evidence concerning the source of water infiltration and to allocate responsibility amongst themselves was compromised" Harborview Office Center, 2006 Wis. App. 149, * 14.

The owner appealed. The Wisconsin Appellate Court affirmed the trial court.

The governing rule is that "There is a duty on a party to preserve evidence essential to the claim being litigated." The parties had focused on the windows as the cause. The owner never notified the parties that the owner's expert had changed his opinion and was ordering remediation of the V-grooves. Here, the owner's conduct was "egregious because it was a flagrant, knowing disregard of the judicial process" Harborview Office Center, 2006 Wis. App. 149, * 17-18.

The Appellate Court was "sensitive to the fact that [the owner] has spent over $1,700,000 in remediation and now may not be able to recover its expenses."

However, under the facts of the case, dismissal was appropriate (Harborview Office Center, 2006 Wisc. App. 149, * 31).


John S. Mrowiec is a partner with Chicago-based Conway & Mrowiec, a construction and public contracts law and litigation practice. He may be reached at (312) 658-1100. For information, go to the firm's Web site at www.cmcontractors.com.

 


 Click here for more Construction Law News >>



advertisement


 


Sponsors

© 2008 The McGraw-Hill Companies, Inc.
All Rights Reserved