News
 Association
 Law/Courtroom
 Building
 Design
 Infrastructure
 Personnel
 Illinois
 Indiana
 Wisconsin
 Submit News





Construction Law - August 2006

Importance of Timely Change Orders Shown


By John S. Mrowiec


Construction contracts typically provide that a contractor is not to perform changed work and the contract price or contract time may not be increased without a written change order.

In practice, however, those words of the contract sometimes are ignored. It is common for contractors to perform extra work and to submit a formal change order request later. Many owners and contractors are content to administer contract modifications that way.

A less-than-formal attitude on the change-order process worked for one contractor and one owner on more than 30 projects.

But on what would be their last project, a dispute about the quality of the contractor's work arose. The failure to submit contemporaneous change-order requests then became a major issue.


Nearly Done Project Terminated

In Welton Ventures Limited Partnership v. Project Coordinators, Inc., 2006 Wis. App. LEXIS 424 (4th Dist. May 11, 2006), the owner, Welton Ventures LP, terminated a construction contract for an office and warehouse at 90 percent completion. The contractor, Project Coordinators Inc., thereafter submitted requests for 34 change orders seeking $573,211. Litigation ensued with various claims between the parties.

A major issue was whether the contractor was entitled to any payment for the late submitted change order requests. The contractor sought $111,070 for breach of contract for progress and retainage payments. (The adjusted contract price included three signed change orders.) For the change order requests, the contractor sued the owner for $573,211 under the theory of "unjust enrichment."

After a jury trial, the jury awarded the contractor $111,070 on the contractor's breach of contract claim and $203,287 of the $573,211 "unjust enrichment" claim. The jury awarded the owner $42,404 in damages on the owner's breach of express warranty claim. (There were awards on other contractor claims not the subject of this article.)

The trial court denied the owner's motion to invalidate the jury's verdicts in favor of the contractor. The owner appealed on various theories. For purposes of this article, we focus only on the owner's contention that the jury's award on the late change order requests under the contractor's theory of "unjust enrichment" was improper.

The owner argued that recovery for "unjust enrichment" is always improper when there is a written contract on the same subject matter. The Welton Ventures court first acknowledged that the owner was correct that the general rule was that a written contract on the same subject precludes an "unjust enrichment" recovery.

But what made this case different was that the contractor was seeking completely different amounts for completely different damages in its breach-of-contract and unjust-enrichment claims: One claim was for unpaid contract balance and one claim was for the late change order requests. There was no double-count.

'Could Have, Should Have'

Welton Ventures acknowledged that instead of the "unjust enrichment" theory, the contractor "could have, and perhaps should have" used conventional contract-based theories to seek recovery for the extra work.

The contractor could have contended that the owner waived the contract's written change order provisions under the theory of the parties' course of dealing on their many previous projects. Or, the contractor could have argued that the parties had separate "contracts implied in fact" for the additions and modifications.

While those are the conventional ways that contractors overcome the written change order provision, the contractor's theory was held valid in this case because the Welton Ventures court was not persuaded that the jury awarded more to the contractor than it would have awarded under the conventional theories, Welton Ventures, 2006 Wis. App. LEXIS 424, * 28-29 and n.9. In other words, "no harm, no foul."

The owner also contended that the contractor's unjust enrichment damages proof did not satisfy the requirement of proof of the amount of "benefit conferred on the owner."

The contractor's proof was the contractor's cost to perform the extra work.

Although damages for "unjust enrichment" must be measured by the benefit conferred on the owner, the Welton Ventures court noted that one way the law measured that benefit is "the reasonable value to the other party of what he received in terms of what it would have cost him to obtain it from a person in the claimant's position" Welton Ventures, 2006 Wis. App. LEXIS 424 at * 33 n.10 quoting Restatement (Second) of Contracts § 371 (1981).

Moreover, it was not as if the jury blindly accepted the contractor's evidence that all the cost "translated into a benefit to" the owner. After all, the jury awarded only $203,287 of the $537,211 requested, Welton Ventures, 2006 Wis. App. LEXIS 424 at * 31.

The appellate court affirmed the jury's verdict in favor of the contractor. Welton Ventures reminds us of two important legal principles about parties' failure to follow the contractual change-order process by performing modifications in advance of the written change order requests and issuance of change orders: (1) an owner might be held to have waived the written change order requirements by owner's conduct, and (2) a contractor's recovery might be less than if contractor had obtained timely signed change orders.

The failure to submit contemporaneous change-order requests then became a major issue.


John S. Mrowiec is a partner with Chicago-based Conway & Mrowiec, a construction and public contracts law and litigation practice. He may be reached at (312) 658-1100. For information, go to the firm's Web site at www.cmcontractors.com.

 


 Click here for more Construction Law News >>



advertisement


 


Sponsors

© 2008 The McGraw-Hill Companies, Inc.
All Rights Reserved