|
The Risk of Long-Lead-Item Expenses
By John S. Mrowiec
On privately owned construction projects, it has become increasingly
common for contractors to begin ordering long-lead items of
materials and equipment before the owner has obtained a building
permit.
Care is warranted. Who bears the risk of payment for those
"long-lead items" if the permit is not issued and
the project ultimately does not proceed?
An example of such a dispute is Otis Elevator Co. v. Fulcrum
Construction Co., 2006 Wis. App. LEXIS 661 (Dist. One, July
25, 2006).
Medical Office Project
On Dec. 8, 1999, Fulcrum Construction Co., as general contractor,
signed a contract to construct a medical building for Capital
Medical Development LLC, the owner. Prior to entering into
the contract, the contractor had negotiated with Northwestern
Elevator Co., a predecessor of Otis Elevator Co., for the
supply and installation of a hydraulic passenger elevator
based on Sept. 17, 1999, elevator drawings supplied by the
owner's architect.
By a Nov. 23, 1999, letter, the elevator subcontractor advised
that the elevator components had to be ordered 16 weeks prior
to installation, asked whether the architect's drawings had
changed in the interim and requested that contractor sign
an enclosed Elevator Ordering Information form.
The contractor did not sign the Elevator Ordering Information
form, but the Architect did on Dec. 21, 1999. On Jan. 25,
2000, the contractor and elevator subcontractor entered into
a written subcontract.
The subcontract incorporated the General Conditions of the
general contract.
Based on the quotations of the General Conditions in the Fulcrum
Construction decision, the General Conditions appear to be
the American Institute of Architects form.
On Feb. 3, 2000, one week after entering into the subcontract,
the elevator subcontractor ordered elevator components to
meet the required installation date of June 6, 2000. On March
15, the contractor notified all subcontractors that, because
of a problem obtaining a building permit, the project had
been suspended. The contractor's notice to the subcontractors
expressly stated that the project was "not terminated."
On April 12, 2000, the elevator subcontractor submitted shop
drawings and advised that it could not apply for an elevator
permit without approval. The shop drawings were never approved.
(The Fulcrum Construction decision does not state whether
the shop drawings were rejected.)
On May 18, 2000, the elevator subcontractor invoiced the contractor
for the elevator components. The contractor refused to pay
contending that contractor had advised that no components
should be ordered without approved shop drawings. The owner
canceled the project. (The decision again is unclear on whether
owner's cancellation preceded contractor's letter with the
"no approved shop drawing" rationale for non-payment.)
Elevator Contractor Sues
The elevator subcontractor sued the general contractor. The
contractor relied on Section 3.12.7 of the General Conditions:
"The [Subcontractor] shall perform no portion of the
Work for which the Contract Documents require submittal and
review of Shop Drawings, Product Data, Samples and similar
submittals until the respective submittal has been approved
by the Architect."
The Fulcrum Construction decision says "the specific
shop drawings required for the elevator were described in
detail in the four pages of the Project Manual" devoted
to the elevator specifications (Fulcrum Construction, 2006
Wis. App. LEXIS 661, *17).
The contractor moved for summary judgment that no amount was
owed to elevator subcontractor for the elevator components.
The elevator subcontractor agreed that it was a responsible
to submit shop drawings to receive an elevator permit and
prior to installation but not before ordering.
According to the elevator subcontractor, submission of product
data was all that was required.
The trial court agreed with the contractor and dismissed elevator
subcontractor's complaint. The elevator subcontractor appealed.
On appeal, the court reviewed the Contract Documents and found
them to be ambiguous. The Fulcrum Construction court believed
3.12.17 of the General
Conditions reasonably could be read to require approval of
shop drawings prior to ordering of components, as the contractor
contended, or merely approval of product data submissions
prior to ordering and approval of shop drawings prior to installation,
as elevator subcontractor contended.
The appellate court found a contradiction regarding the parties'
intent in the evidence submitted on contractor's summary judgment.
That created a question of fact that could not be resolved
without a trial.
To determine which interpretation applied in this particular
instance, the Fulcrum Construction trial court should consider
at a trial "parol evidence" of the parties' conduct
prior to entering into the written subcontract. Because a
trial was necessary to determine the parties' intent, the
trial court grant of summary judgment was reversed (Fulcrum
Construction, 2006 Wisc. App. LEXIS 661, *18).
The Fulcrum Construction fact pattern is silent about some
intriguing questions:
Did the owner pay general contractor a termination settlement?
If not, was the contractor pursuing owner for payment?
(The 1997 edition of the AIA General Conditions provides the
owner the right of "termination for convenience"
with the obligation to pay for ordered or installed materials
and equipment, among other things. The 1987 edition of those
General Conditions does not address a convenience termination
but, under that edition, the inability to obtain a permit
might be an owner breach probably dependent on the Notice
to Proceed language of the particular Contract.)
If the owner did pay a termination settlement, did the owner
refuse to pay for the ordered elevator components? Did the
four pages of specifications supposedly listing the required
submittals distinguish between "product data" and
"shop drawings" for elevator operating components?
When drafting contract documents or when ordering materials,
parties should anticipate the possibility that the project
might not proceed. Clarity regarding liability for payment
in that event is important.
John S. Mrowiec is a partner with
Chicago-based Conway & Mrowiec, a construction and public
contracts law and litigation practice. He may be reached at
(312) 658-1100. For information, go to the firm's Web site
at www.cmcontractors.com.
|