|
Who's on the Whose Team with Alternative Delivery Methods?
By John S. Mrowiec
A traditional way of designing and building a project is
the "design-bid-build" method. An owner hires an
architect to prepare schematics, design development and construction
documents.
When the construction documents are complete, the owner seeks
bids from potential general contractors. Then, the owner selects
a general contractor who would hire subcontractors and build
the work as designed in the construction documents.
With the goals of decreasing the time to design and construct,
achieving better constructability and lowering construction
costs-or to establish a single entity responsive to the owner-alternative
delivery methods have arisen. Among possible alternatives
to "design-bid-build" are construction management,
design/build and hybrids of those approaches.
Sometimes an owner might engage an architect and before the
design is complete, assign the owner-architect agreement to
a design-builder.
Thereafter, the owner still might be communicating with the
architect about design intent, the budget and design changes.
From whom is the architect to take direction and who pays
the architect's fees? That is a simplified description of
the delivery method the parties attempted to use and the ensuing
disputes in a recent project gone awry, City of Coralville
v. FaulkerUSA, Inc., 2006 U.S. Dist. LEXIS 91819 (S.D. Iowa,
Dec. 15, 2006).
The city of Coralville established the Coralville Hospitality
Corp. as a nonprofit corporation to own and operate a to-be-designed
and constructed Marriott hotel and conference center. The
city and the operator solicited requests for proposals from
developers. FaulknerUSA Inc. was the successful respondent.
It is impossible due to space limitations to describe fully,
and without potentially erring, the "menu of contracts
guid[ing] relationships" among the various parties, Coralville,
2006 U.S. Dist. LEXIS 91819, *6.
The operator entered into a "Memorandum of Understanding"
under which the respondent agreed to design and build the
project for a preliminary budget of approximately $57 million.
The design/builder was to subcontract with an architect for
the design pursuant to a fee schedule. Thereafter, the operator,
not the design/builder, entered into an architectural design
services agreement with an architect, Cole + Russell Architects
Inc.
Suit Filed, Sought Public Bidding
A group of contractors filed litigation seeking to require
public bidding.
Apparently to address the public bidding issue, the operator
entered into a "Preconstruction Services Agreement"
with the design/builder. Under that agreement, the design/builder
would serve as a "construction manager," and the
field construction work would be bid.
Under the preconstruction services agreement, the construction
manager would earn a fee of $475,000 for preconstruction work
"plus the direct cost of any related expenses of construction
manager in connection with the performance of the preconstruction
work," Coralville, 2006 U.S. Dist. LEXIS 91819, *61-62.
That agreement attached a cost breakdown exhibit budgeting
$2,242,000 for architectural and engineering fees. The Preconstruction
Services Agreement permitted changes in the scope of the preconstruction
work only by written change orders signed by the operator.
The Preconstruction Services Agreement listed a preliminary
budget of $60,213,000 with contemplated future negotiations
to establish a final budget within 5% of that figure. It also
contemplated entry into a subsequent
"Construction Manager Agreement" with construction
manager, after acceptance of the appropriate bid for the construction
work, for construction manager to manage, but not perform,
the field construction work.
As part of the Preconstruction Services Agreement, the operator
assigned the Operator-Architect Design Agreement to the construction
manager. At that time, the operator had paid the architect
$955,233.
Even though there already was the assignment of the Architect
Agreement, the construction manager issued a Letter Agreement
to the architect authorizing the architect to proceed under
a draft Design Services Agreement with fees not to exceed
$1,770,779. The construction manager and architect began negotiating
the Design Service Agreement and ultimately finalized its
terms.
A portion of the project, excluding parking ramps and other
items, was let for public bids. The construction manager had
predicted prices of approximately $37 million for that project
portion.
However, the three bids received ranged from $50 million to
$54 million.
After some further attempts to achieve the budget, the operator
terminated the construction manager. Ultimately, the city
and operator engaged others to build the project.
The architect claimed $667,206 in unpaid fees from the construction
manager.
The operator claimed $2.7 million from the construction manager
for return of amounts previously paid the construction manager
and its consultants.
Suit, Countersuit Filed
The city and operator sued the construction manager, and the
architect sued the construction manager for the unpaid fees.
The construction manager denied that it must return its compensation
and sued the city, operator and operator's representative
for the fees being sought by the architect and sued the architect,
too. The legal theories asserted by the parties were numerous.
After discovery, the parties moved for summary judgment on
some of the theories on the various claims.
The Coralville decision is 138 pages. It involves such subjects
as the construction manager's admitted failures to change
the projected budget amounts in periodic reports to operator
to address likely bids as the design status progressed, limitation
of liability, pass-through, conditional payment, rescission
of contracts and the consequences of construction manager's
failure to request preconstruction services change orders.
Absent from the Coralville decision was any discussion of
any argument that the architect had failed to design within
budget.
I am addressing only one of the issues raised by the chosen
delivery system and the way the process occurred.
The construction manager argued that one of the reasons both
the bid prices were over budget and the architect should not
be compensated was that the operator had communicated design
changes directly to the architect who incorporated the changes
without the construction manager's knowledge or consent.
The construction manager contended the architect breached
the Design Services Agreement by (1) "communicating directly
with representatives" of [the operator] and the City
[in a manner] "far beyond mere communications,"
and (2) "performing work as directed by the city and
[the operator] without consulting with or seeking approval
from Construction Manager," Coralville, 2006 U.S. Dist.
LEXIS 91819, *130-33.
The architect moved for summary judgment on construction manager's
claim.
The Design Services Agreement specifically contemplated that
"the design process for the Project is collaborative"
and that nothing in the Design Services Agreement was intended
to limit the free flow of information among the architect,
construction manager, operator, city, operator's authorized
representative, Marriott, and the trustee [for bond financing],"
Coralville, 2006 U.S. Dist. LEXIS 91819, *132.
The Coralville court cited that language in agreeing with
architect regarding the construction manager's "direct
communication" theory. Under the language of the Design
Services Agreement, communication between the architect and
operator was not a breach by the architect of its agreement
with the construction manager.
Agreement's Language Key
The Design Services Agreement, though, contained additional
language. That agreement gave the construction manager sole
"authority and responsibility to issue comments to the
[architect] that will be considered an approval of architect's
deliverables, and "to maintain the Design Schedule and
avoid unnecessary redesign efforts by [Architect], [Construction
Manager] will be the single point of formal approval for [Architect's]
Deliverables," Coralville, 2006 U.S. Dist. LEXIS 91819,
*134-35.
The Coralville court read the "collaborative design"
language together with the construction manager "authority"
and "approval" language. While direct communication
between the operator and architect was encouraged and permitted
by the Design Services Agreement, the Coralville court made
the distinction that "Insofar as [Architect] accepted
any 'approval' of its
Deliverables by either the City or [the Operator] by incorporating
the suggestions or requests without funneling these suggestions
or requests through [Construction Manager] for approval, that
scenario would constitute a breach of the Design Services
Agreement," Coralville, 2006 U.S. Dist. LEXIS 91819,
*137.
There was deposition testimony cited with a different motion
which could be read as knowledge and approval by the construction
manager of some additional services by the architect for integration
of operator-directed changes. But because architect had chosen
to challenge only the legal theory and not the facts as alleged
by the construction manager, the court denied the architect's
motion for summary judgment.
The construction manager may proceed to trial to attempt to
prove the facts to support the claim that the architect breached
by performing services in integrating the city's or operator's
design suggestions (that might otherwise have been compensable
additional services) without first giving the construction
manager the opportunity to consent.
John S. Mrowiec is a partner with Chicago-based Conway &
Mrowiec, a construction and public contracts law and litigation
practice. He may be reached at (312) 658-1100. For information,
go to the firm's Web site at www.cmcontractors.com.
|