|
Perils of Partial Waivers for Progress Payments
By John S. Mrowiec
Contractors and subcontractors commonly sign partial waivers
either in advance of or in exchange for progress payments.
Typically, these waive the payment recipient's right to a
mechanics lien claim to the extent of the progress payment
or for work to a specified date.
Sometimes, the contract or subcontract requires that the recipient
of the progress payment sign a designated form of waiver.
These designated forms might purport to do more than merely
waive mechanics lien rights, depending on the form. Beyond
waiving mechanics lien rights, the form might also provide
that the signing party "releases" all rights to
any "causes of action, claims, suits and demands"
that the signing party might have against the prime contractor
and owner.
Such was the Partial Waiver and Release Form at issue in Advance
Mechanical Contractors, Inc. v. Southeast Wisconsin Professional
Baseball Park District, 2007 Wis. App. LEXIS 57 (Dist. One
Jan. 30, 2007).
Umpire Needed
SWPBPD involved a payment dispute under a subcontract at Miller
Park, the home of the Milwaukee Brewers. Advance Mechanical
Contractors Inc. was the above-ground plumbing subcontractor.
HCH Miller Park Joint Venture, a joint venture of the Hunt
Construction Group, the Clark Construction Group, Inc. and
Hunzinger Construction Co., was the construction manager.
Southeast Wisconsin Professional Baseball Park District, a
municipal corporation, was the owner.
Under the subcontract, the subcontractor was to submit a monthly
progress payment application along with a fully-executed affidavit
and a Partial Waiver of Claims and Liens and Release Form.
If the subcontractor wished to request additional compensation,
the subcontract required submission of a written change-order
request to be designated on an Advance Quote Log.
The Partial Waiver and Release Form provided that the subcontractor
"agreed to release all rights to any 'causes of action,
claims, suits and demands' that it could bring against [the
construction manager] and [owner] for the work completed through
the date of the Payment Application," SWPBPD, 2007 Wis.
App. LEXIS 57 at *6.
Importantly, though, the Partial Waiver and Release Form allowed
the subcontractor "to exempt from the release particular
claims and to preserve them by listing them on Exhibit A to
the Partial Waiver and Release Form," SWPBPD, 2007 Wis.
App. LEXIS 57 at *7.
Deaths Rock Project
The subcontractor began work on the stadium in 1998. On July
14, 1999, a crane collapsed on the partially completed stadium,
killing three iron workers, injuring others and causing a
13-month delay. The subcontractor incurred extended duration
damages and extra costs to remove and replace work damaged
by the collapse.
The owner had procured a builders risk insurance policy. On
Feb. 28, 2001, the subcontractor settled its claim against
the insurer for extended home office overhead, interest, lost
profits and extra work for payment of $1,600,000, SWPBPD,
2007 Wis. App. LEXIS 57 at *8.
The subcontractor employed the Advance Quote Logs throughout
the project to request additional compensation. Admittedly,
though, the subcontractor never attached the Advance Quote
Logs to any of the monthly Partial Waiver and Release Forms
submitted with payment applications.
Prior to settling with the builders risk insurer, the subcontractor
filed two public improvement lien claims alleging it was owed
$2,478,952 and sued the construction manager and owner to
enforce the claims. Within two months of settling with the
builders risk insurer, and after completion of the project,
subcontractor increased its damages claim by nearly $2,000,000
for "extra overhead due to the increased duration of
the project," "loss of business/gross profit due
to the extended contract duration," "labor inefficiencies
after the crane collapse" and "extra engineering
work."
After discovery and unsuccessful settlement negotiations and
mediation, both the construction manager and owner moved for
summary judgment. Among other things, they argued that the
subcontractor had released all claims it now asserted by failing
to attach an Exhibit A listing those claims exempt from each
monthly Partial Waiver and Release Form. The trial court agreed.
Judgment Against Sub
Not only did the subcontractor lose its claim, but the trial
court entered judgment against the subcontractor for nearly
$1 million in attorneys' fees and costs of the construction
manager and owner. The subcontractor appealed.
The subcontractor argued that it had not released any of the
claims for which it sued. The subcontractor's first argument
was that the Partial Waiver and Release Form expressly related
solely to "work performed in the construction of the
Project," that phrase was "defined," according
to the subcontractor, in an earlier section of the Form as
"work . . . for which payment is due" and that claims
of extra work, not yet being agreed approved written change
orders, were not actually "due" so could not be
released.
The SWPBPD appellate court rejected the subcontractor's argument.
First, the court reasoned, the subcontractor's interpretation
effectively would allow an implicit exception, unapproved
claims for extra work or damages, to swallow the specific
exclusion for listed claims. The listing requirement would
be meaningless, the court said, if all unapproved claims were
implicitly excluded from the release.
Second, the SWPBPD appellate court found that the subcontractor's
"definition" was not a definition at all. It referred
instead to the period covered by the payment request.
The subcontractor contended that it was unaware of the need
to attach the Advance Quote Logs to the release to preserve
those claims. The court quickly dispatched that argument emphasizing
that it was the subcontractor's "responsibility to read
the contents of the Partial Waiver and Release Form,"
SWPBPD, 2007 Wis. App. 57 at *25.
The SWPBPD court agreed with the subcontractor that the Partial
Waiver and Release Form did not support an award of attorneys'
fees to the construction manager and owner. The form only
provided for attorneys' fees for claims by the subcontractor's
lower tier subcontractors and suppliers.
Unfortunately for the subcontractor, though, the Appellate
Court held that the subcontract language itself provided for
attorneys' fees to the construction manager and owner as prevailing
parties. Regarding the reasonableness of the amount of fees,
SWPBPD held it was not an erroneous exercise of the trial
court's discretion to have found that "the case required
a great deal of time for discovery and dealt with complex
legal issues that required more skilled attorneys."
The SWPBPD affirmed the trial court's judgment against the
subcontractor.
While never explicitly basing its holding or any reasoning
on what the court characterized as a "concession,"
it is difficult to avoid the implication that the court might
have been influenced by the following the court chose to include
in a footnote: "During discovery, [the Subcontractor]
conceded that in recovering $1,600,000 [from builders risk
insurer], it actually earned a $600,000 profit," 2007
Wis. App. 57 at *8 n. 2.
Regardless, while there might be particular exceptions applicable
in particular circumstances, SWPBPD teaches that a payment
recipient who fails to read a monthly Partial Waiver and Release
Form and to reserve claims does so at its peril.
John S. Mrowiec is a partner with Chicago-based Conway &
Mrowiec, a construction and public contracts law and litigation
practice. He may be reached at (312) 658-1100. For information,
go to the firm's Web site at www.cmcontractors.com.
|