|
How Strict are Deadlines for 'Constructive Changes?'
By John S. Mrowiec
Construction industry participants are well aware of the
existence of contractual notice provisions. They usually set
"deadlines" for notice of events constituting changes
or claims and sometimes for quantification of the change or
claim.
Much less well understood is how notice provisions actually
are applied by the courts. Do the courts apply these provisions
literally or are there exceptions to strict application of
the "deadlines?"
A recent U.S. Federal Claims Court decision illustrated the
issue, AAB Joint Venture v. United States, 2007 U.S. Claims
LEXIS 22 (Feb. 2, 2007).
Project in Israel
AAB Joint Venture was the design-builder reporting to the
U.S. Army Corps of Engineers for a storage and logistics complex
to be constructed in Israel for use by the Israeli Defense
Force. The design-builder subcontracted the earthwork operations
and separately subcontracted the testing of earthwork densities.
Despite the design-build nature of the contract, the Corps
provided particular specifications for earthwork. The Earthwork
Division provided that backfill material was to be compacted
to a specified maximum density, depending on location, according
to modified American Association of State Highway and Transportation
Officials requirements.
The design-builder's testing subcontractor informed the design-builder
that it could not test 6-in. fill material using the specified
standard. Accordingly, on Jan. 4, 2002, the design-builder
submitted a Request for Information. The Army Corps responded,
stating that the exact material and testing standards to be
used were the design-builder's responsibility to determine.
Based on the response to the RFI, the design-builder instructed
its earthwork subcontractor to use a 3-in. material compacted
using the specified AASHTO standard. The earthwork subcontractor
incurred additional costs.
On Dec. 17, 2003, after the project was complete, the design-builder
submitted a certified claim to the contracting officer in
the amount of $916,895 for the earthwork subcontractor's additional
costs. Thereafter, the design-builder filed suit against the
United States in the U.S. Court of Claims.
A 'Constructive Change'
The design-builder contended that the Army Corps' response
to the request for information constituted a "constructive
change," entitling the design-builder to an equitable
adjustment. The federal construction contract provides for
change orders or constructive changes. A "constructive
change" is the following:
"(b) Any other written or oral order (which, as used
in this paragraph (b), includes direction, instruction, interpretation
or determination) from the Contracting Officer that causes
a change shall be treated as a change order under this clause;
provided that the Contractor gives the Contracting Officer
written notice stating (1) the date, circumstances, and source
of the order and (2) that the Contractor regards the order
as a change order," 48 C.F.R. 52.243-4(b) (2005) (emphasis
added).
Following discovery, the government and the design-builder
each moved for summary judgment. Among other arguments, the
government argued that the design-builder's claim should be
barred because of the design-builder's failure to give the
written notice required by the changes clause of the contract.
In addition to the notice required by subsection (b), the
change clause further provides regarding notice:
"(d) If any change under this clause causes an increase
or decrease in the Contractor's cost of, or the time required
for, the performance of any part of the work under this contract,
whether or not changed by any such order, the Contracting
Officer shall make an equitable adjustment and modify the
contract in writing. However, except for an adjustment based
on defective specifications, no adjustment for any change
under paragraph (b) of this clause shall be made for any costs
incurred more than 20 days before the Contractor gives written
notice as required. In the case of defective specifications
for which the Government is responsible, the equitable adjustment
shall include any increased cost reasonably incurred by the
Contractor in attempting to comply with the defective specifications.
"(e) The contractor must assert its right to an adjustment
under the clause within 30 days after (1) receipt of a written
change order under paragraph (a) of this clause or (2) the
furnishing of a written notice under paragraph (b) of this
clause, by submitting to the Contracting Officer a written
statement describing the general nature and amount of the
proposal, unless this period is extended by the Government.
The Statement of proposal for adjustment may be included in
the notice under paragraph (b) above," 48 C.F.R. 52.243-4(d)
and (e) (2005) (emphasis added).
The design-builder acknowledged that it had not given written
notice to the contracting officer but argued that notice was
not required under the circumstances because:
(1) The government had actual knowledge of the facts constituting
the constructive change.
(2) The government was not prejudiced by the lack of formal
notice (and the burden of showing prejudice lies with the
government).
(3) The constructive change resulted from defective specifications.
Court Ruling
The AAB Joint Venture court conceded that federal construction
contract "notice provisions should 'not be applied too
technically and illiberally where the Government is quite
aware of the operative facts,'" AAB Joint Venture, 2007
U.S. Claims LEXIS 22 at *28 quoting Hoel-Steffen Construction
Co. v. United States, 456 F.2d 760, 768 (Ct. Cl. 1972).
The court also agreed with the principle that "the notice
provision may not be strictly enforced if the contracting
officer gives an oral directive knowing full well that it
differs from the specifications," AAB Joint Venture,
2007 U.S. Claims LEXIS 22 at *29 citing Calfon Construction,
Inc. v. United States, 18 Cl. Ct. 426, 438 (1989).
When a claimant alleges a constructive change "notice
of the claim need not be presented 'within the specific number
of days allowed' by the Changes clause," AAB Joint Venture,
2007 U.S. Claims LEXIS at *31 quoting Jo-Bar Mf'g Corp. v.
United States, 535 F.2d 62, 66 (Ct. Cl. 1976). Nevertheless,
"the filing of a claim within the time period of administration
of the contract is clearly a prerequisite," Id.
Yet, "[I]n contracts, where lack of notice by the contractor
forecloses less costly alternative solutions or avoidance
of contractor claims by the government, then the notice requirement
is likely to be enforced," AAB Joint Venture, 2007 U.S.
Claims LEXIS 22 at *29 citing Calfon Construction, 18 Cl.
Ct. at 439.
The Claims Court noted that in previous cases, the court had
concluded that knowledge by the contracting officer that problems
in contract performance is not the same as notice of a specific
monetary claim against the government, AAB Joint Venture,
2007 U.S. Claims LEXIS at *30 (citing cases).
The AAB Joint Venture court pronounced that "the overriding
principle to be followed is that '[w]ritten notice as to constructive
changes must be supplied by the contractor for such time that
the Government would suffer if not apprised of the facts,'"
AAB Joint Venture, 2007 U.S. Claims LEXIS at *29 quoting Calfon
Construction, 18 Cl. Ct. at 438.
Contracting Officer Not Informed
The Claims Court found no evidence that the contracting officer
had any knowledge that the design-builder considered the response
to the RFI to constitute a constructive change. Indeed, the
court accepted that it was likely that the contracting officer
thought the response actually relaxed the requirements of
the specifications because after the response, the design-builder
was free to use a different density standard test [but not
a different percentage], AAB Joint Venture, 2007 U.S. Claims
LEXIS at *29-30.
Likewise, there was no evidence that the design-builder stated
orally or in writing to the contracting officer that it intended
to seek monetary damages as a result of the alleged change.
Nor did the design-builder submit a claim during the time
the contract was being administered.
The AAB Joint Venture court could not say that the government
was not prejudiced by the delayed filing of the claim or that
the government could not have at least partially remedied
the impact if it had received earlier notice.
Therefore, the Claims Court granted that portion of the government's
motion for summary judgment for lack of notice of the constructive
change arising from the RFI response, AAB Joint Venture, 2007
U.S. Claims LEXIS at *31.
The court denied the government's motion for summary judgment
on the design-builder's separate "defective specifications"
claim. The court distinguished a claim of constructive change
arising from the "directive" (the response to the
RFI) from a claim regarding the originally defective specifications
themselves. The government might have been prejudiced by lack
of notice from the constructive change but subclause (d) carved
out claims of "defective specifications."
John S. Mrowiec is a partner with Chicago-based Conway &
Mrowiec, a construction and public contracts law and litigation
practice. He may be reached at (312) 658-1100. For information,
go to the firm's Web site at www.cmcontractors.com.
|