|
Soldier Field, Chicago
Squeezing a modern stadium within the
confines of an existing historic structure was a key issue
in the redevelopment of Soldier Field.
A cross section had to be developed that was about 80 ft.
narrower than a typical National Football League arena. An
asymmetrical solution was developed with suites stacked on
one side and cantilevered seating bowls. This created seating
believed to be the closest to the field among all NFL arenas.
The long spans and cantilevers used throughout accommodate
the existing structure's width and height restrictions and
ensure unobstructed views.
The grandstand cantilevers extend 50 ft. from the last brace
point. The south scoreboard cantilevers 90 ft. over the seating
deck, and the north scoreboard cantilevers 120 ft. over the
deck.
To maximize patron comfort from vibrations, tuned mass dampers
were added. These monitored air shock, and spring-controlled
damping systems counteract structural and rhythmic deflections
and vibrations.
Because of the stadium's architectural and structural constraints,
the mechanical system routing required every duct to be coordinated
with beam penetrations. In all, Soldier Field has thousands
of penetrations.
The beam penetrations raise issues in themselves. Each was
studied to ensure the stadium's structural integrity. The
mechanical systems were then coordinated to conform to the
size requirements for each penetration in the steel. All other
mechanical, electrical and plumbing work was coordinated to
accommodate the tight interstitial space.
Game Plan for Schedule
A directive to the construction team was for the Chicago
Bears football team, the stadium's main lessee, to play only
one season away from Soldier Field.
The construction schedule was shortened from the typical 26
to 28 months to only 20 months. The existing stadium within
the colonnades would also need to be demolished during this
time.
Construction kicked off four hours after the Bears' playoff
loss to the Philadelphia Eagles on Jan. 20, 2002, with a schedule
that tracked the move-out process in 15-minute increments.
Demolition was executed on a 24-hour, seven-day-a-week timetable.
Nine months of site preparation preceded this period. Activities
that included power feed relocation, drainage, demolition
of a six-story office building and asbestos abatement occurred
during the time the existing stadium and adjacent museum campus
were operational.
By designing a structural steel frame that mounted directly
to the pile caps, the erection of the stadium frame was expedited.
Due to the lack of sufficient space in the bowl for cranes,
coordination of the erection of the precast concrete stadium
risers and the structural steel was done by erecting the steel
during the day and the precast at night.
Sitework and Schedule
The site is a landfill containing debris from the Great Chicago
Fire of 1871. Instead of being removed, the fill was used
to create berms and a sledding hill.
Asbestos abatement was performed on the known conditions in
the existing stadium crawlspace. During the start of demolition,
a significant amount of asbestos was also discovered in the
soil under the stadium.
The abatement of the newly discovered asbestos could not affect
the schedule. Mass demolition and abatement of the hazardous
soil below the stadium were performed simultaneously while
maintaining the 20-month schedule.
The surface of the bowl area was not a suitable one for construction
due in part to the debris from the Chicago Fire, the need
for asbestos abatement and the location of the water table
less than 3 ft. below. A working surface for multiple cranes
was created by using concrete rubble from the demolition.
The new stadium is founded on driven steel H-piles. Because
the existing historic structure constrained the project on
three sides, performing the foundation work inside the existing
structure required close coordination between the excavation,
pile and concrete subcontractors.
The process included close monitoring of the pile driving
operation with the use of vibration sensors and the installation
of drilled micro-piles where the piles were close to the existing
structure.
Moving Down Field
The project team was required to maintain 2,500 parking spaces
of the original surface parking area for visitors and guests
of the remaining museum campus, including the McCormick Place
Convention Center, John G. Shedd Aquarium, Adler Planetarium
and Field Museum of Natural History.
The Soldier Field project had only one ramp for material access,
and that was installed late in the process. The process before
the ramp was to make use of an existing oversize gate on the
south and use cranes and two material hoists to move material
into the suite levels and upper concourses.
About $100 million of infrastructure work was performed concurrently
with the $400 million on the stadium and integral 2,500-car,
four-level underground North Parking Garage.
The jury said, "Regardless of how you feel about the
design of the outside of this stadium, when you go inside,
there's not a bad seat in the house. What they have done in
20 months is amazing. It couldn't have been done without teamwork.
Permitting was an achievement. They had someone living at
City Hall.
"On the design side, they cut out time by designing in
three dimensions and skipping shop drawings. All contractors
had to literally jump in and write their own requests for
information and then answer them. The geometry is too difficult
to comprehend.
"Even though the design is an atrocity, the fact that
they are playing in the stadium is amazing. Everyone had to
work together to make that happen."
Return
to Best of 2003 list
|