|
General Mitchell International Airport Parking Structure, Milwaukee
The General Mitchell International Airport
Parking Structure has 3,000 parking spaces.
The $81 million project also included infrastructure improvements
to serve airport needs in the future.
The 1.1 million-sq.-ft. addition was constructed immediately
north of the existing parking structure. It is separated by
a six-story, 700-ft.-long pedestrian access corridor, which
allows users a direct path to the terminal.
User friendliness was an important goal for the design, and
cracking was a key area of focus.
Cracking is unsightly, may also result in leaking of salts
onto cars below and require repairs resulting in disruption
and lost revenue. The concrete mix was designed to prevent
contamination by salt-laden water and runoff because it minimizes
flexural cracking. A combination of fly ash and slag was used
in the mix, and the top layer has an epoxy coating for reinforcing.
Pretty Parking Structure
It was important that the exterior appearance carefully blend
the new and existing structures. The canted, perforated white
panels added around the structure in combination with the
large, circular helixes on the west face add an attractive
design element, while minimizing the impression of a large
gray concrete building.
The power plant serving the airport was demolished and replaced
by a new $12 million facility with 50 percent more capacity
to make room for the structure. Site utilities, roadways and
several other buildings were also relocated for the same reason.
Activities that included forming, placing, reinforcing, pouring,
post-tensioning, stripping forms and clean up were all done
simultaneously because work areas were so large.
An average of 1,200 cu. yds. of concrete were placed each
day. Reinforced, cast-in-place concrete was selected because
of the design flexibility it allows. Concrete helped to maximize
the available space at the airport grounds because the addition
is bordered by curving and angular roadways on one side and
the existing garage on the other.
The jury said, "This is a nice piece of design and has
good detailing. They effectively brought light and brightness
into the interior spaces. The fact that the project was completed
while it stayed open for business added a degree of complication
that the team solved effectively."
Return
to Best of 2003 list
|