|
Roseland Pumping Station Conversion, Chicago
In 1911 the city of Chicago built the
steam-powered Roseland Pumping Station. With a capacity of
300 million gallons per day, the RPS is the only source of
drinking water for 750,000 people on the city's South Side
and in the southern suburbs.
During the unusually high peak demands in the summer of 1995,
the reliability and operational difficulties of the aging
steam systems become evident. The Chicago Department of Water
Management initiated a fast-track program to upgrade the RPS
pump drives from steam turbines to electric motors.
Contract documents for the incoming electrical system and
standby electrical power required to operate the new electric
motors were prepared.
Work included a new electrical building to house the electrical
medium voltage switch gear, variable frequency drive systems,
diesel- and natural-gas-fueled standby generators and generators
load banks. Rehabilitation affected the existing centrifugal
water pumps, expansion and modifications to the supervisory
control and data acquisition system and modifications to the
existing pump building.
An underground piping and access tunnel was provided between
the new electrical building and the existing pump building.
The design of a water pumping station of the size for Chicago
usually requires 36 to 48 months. Working closely with Department
of Water Management staff, the design period was streamlined
to less than 18 months through regular workshop meetings and
onsite evaluations.
First for Upgrade
The RPS was selected as the first of five steam-driven pump
stations to be upgraded because it, unlike the others, is
isolated geographically and is not augmented by a nearby facility.
It was necessary to restrict the number of pumps that could
be taken out of service at one time for conversion to maintain
the full operation of the pump station at all times.
The length of time a pump would be out of service was also
minimized.
Associated electrical equipment was pre-installed in the new
electrical building so that only the new electric motors and
pump rehabilitation were required to be installed during each
pump's conversion. The project was phased over 3 1/2 years
to facilitate a smooth transition to electric power without
interruption of service.
With the increasing number of electrical power outages in
the area, the electrical system was designed with eight 2,000
KW standby generators - five diesel fueled and three natural
gas fueled ¾ and parallel equipment.
The diesel-fueled standby generator system allows the RPS
to continue full operation through brownouts or complete power
outages. When economically feasible, the natural gas standby
generators can be installed to allow the RPS to reduce electrical
costs by paralleling with the local utility for peak shaving.
Two Water Systems
The RPS serves two separated water distribution systems.
The low-pressure zone supplies water at a nominal pressure
to the low elevation areas of the south and southeast sides
of the city and adjacent suburbs. The high-pressure zone supplies
the high elevation areas of the city and suburbs to the west
of the station.
To meet the widely varying demands of the water distribution
system, separate variable frequency drives were provided for
each pump. The operating system still allows any pump or combination
of pumps to be connected to either distribution system to
maintain a relatively constant water pressure in each system,
thereby reducing the hydraulic shock to the aging water mains.
VFDs also provide power savings.
The conversion from steam to electric pumps will save the
city on estimated $2 million annually by reducing operating
and maintenance costs, in addition to increasing flexibility
and reliability of operation. The majority of the cost savings
is due to the low maintenance required for the electrical
components vs. the aging steam equipment.
The jury said, "This was a huge undertaking. To take
what was there and update it was a tremendous feat. This site
is packed with equipment."
Return
to Best of 2003 list
|