|
Madison Gas and Electric Co. East Campus Substation Screen Wall, Madison, Wis.
The East Campus Substation has delivered
power to the University of Wisconsin and downtown Madison
for more than 30 years.
The substation began to draw ridicule as an eyesore because
of the completion of a pedestrian underpass to the east, volleyball
and soccer fields to the north and the Kohl Center sports
arena, which has the capacity for 17,200 people. The substation
is also located near three dormitories that house more than
1,200 students, many of whom pass the site every day.
The suggestion was made that Madison Gas and Electric Co.,
the substation owner, conceal the facility because of the
influx of pedestrians.
Hiding a Substation
Moving the substation was neither practical nor economical
because it is a critical piece of infrastructure. A two-component
solution was proposed.
A 10-ft.-tall concrete wall with 4-ft.-deep foundation was
installed at the property line on the north, west and southwest
sides to hide the vehicles and equipment in the yard.
The structure is composed of 284 cu. yds. of concrete, including
the below-grade portion.
Also, a system of 1/8-in.-thick nonmagnetic, stainless steel
perforated panels was placed close to the 34-ft.-tall substation
grid. The transparent panels act as a veil giving visual mass
to the substation while still expressing its function.
The custom-designed and -fabricated system comprises 138 4-by-12-ft.
panels and three 2-by-12-ft. panels.
The panels are down lit to illuminate the substation yard.
To deter vandalism, the concrete wall is splayed to create
light coves with lamps washing the wall horizontally.
This eliminates the need for lights on the grounding shining
up, a method that is undesirable for the standpoint of maintenance
and light pollution. The lighting conforms with the Dark Sky
Initiative and university's concern for light pollution.
On game nights at the Kohl Center, the screen wall is illuminated
in the University of Wisconsin's Badger red with a flying
white W.
Electricity Presents Hazard
Designing and building around high voltage was a top concern.
The design team and owner worked together for more than a
year to place architectural elements and make subtle shifts
to avoid below-grade transmission and service lines. The solution
often came within minimum distances allowable by either the
owner or the Occupational Safety and Health Administration.
The use of unconventional materials, like the stainless-steel
panels, was facilitated by the builder's and steel fabricator's
involvement during design. This included providing technical
advice on the means of construction and mock-ups of elements
of the project as well.
The stainless steel screen wall and 34-ft.-tall, 24-ft.-long
concrete wall on the east side are cantilevered out of the
ground and achieve their stability from 4-ft.-dia., 20-ft.-deep
concrete caissons delicately placed to avoid transmission
lines, vaults and duct banks.
Further complicating subsurface work, the substation is sited
on an abandoned rail yard with the foundations of a locomotive
turntable hidden below grade, the location of which could
only be guessed at.
After the foundations were complete, the hazards of high voltage
were still present overhead.
Galvanized steel flange beams serve as the primary load-bearing
and wind-resisting structural elements. These 34-ft.-tall
members were carefully placed, in some cases within 16 ft.
of the active substation grid. Next came placement of beams
spanning the columns from which were hung horizontal channel
girts that serve as the means to affix the stainless steel
panels.
The final major element was the 34-ft.-tall concrete feature
wall. It was cast in a single pour with custom-made forms
to eliminate construction joints.
The jury said, "We wish they would do these screen walls
everywhere. It's a very nice solution."
Return
to Best of 2003 list
|