|
Interstate 65/Interstate 70 Hyperfix, Indianapolis
The combined stretch of Interstate 65/Interstate
70 had never undergone significant repair since it was built
in 1976 and required rehabilitation of 33 bridge decks and
more than 35 lane-miles of pavement.
Additional lanes at two key locations needed to facilitate
greater traffic. The 175,000 vehicles using this section every
day had caused deterioration to the pavement and bridge deck.
The original plan called for a two-phase project in 2002 and
2003 using traditional construction methods: lane closures
and crossovers. But this was estimated to cost $1 million
a day in user costs in traffic backups and lost hours.
After numerous meetings, the bold decision was made to shut
down the interstate for 85 days in the summer of 2003. Engineers
estimated this would take half the time of conventional methods.
Seizing the Opportunity
The window of opportunity was narrow. A complete shutdown
would only be feasible in 2003, the only year during which
Interstate 465, the bypass around the city, had no major lane
restrictions.
The size of the project was immense. In fact, the largest
set of bridge rehabilitation plans in the history of the Indiana
Department of Transportation was prepared.
Cooperation was essential. For instance, INDOT paid more than
$1.7 million to the city for improvements to downtown city
streets and provide extra police to help with the increase
in traffic. The city even delayed some projects to eliminate
other lane restrictions, and a $1 million federal grant was
obtained for park and park-and-ride bus services to downtown.
Many businesses feared the impact the closure would have on
customers. In response, the maintenance-of-traffic plan was
scheduled to allow all exit ramps to downtown and four other
entrance ramps to remain open. The collector-distributor that
runs parallel to the main highway was kept open to serve as
the off ramp to city streets.
The general contractor staffed the project around the clock
for seven days a week. In the end, the project was completed
in 55 days -30 days ahead of schedule. A bonus of $3 million
was paid to the general contractor for the effort.
The jury said, "It was incredible what was accomplished
in such a short period of time. The team was coordinating
constantly on this one."
Return
to Best of 2003 list
|