|
Start 5: Prentice Women's Hospital and Maternity Center
Cost: $502 million
The Prentice Women's Hospital and Maternity
Center will replace the 29-year old facility with the same
name in the Northwestern Memorial Hospital's campus in downtown
Chicago.
Space at the existing hospital has exceeded the capacity for
growth, said Patrick Knightly, senior project manager with
Northwestern. The number of deliveries, for example, has more
than tripled from 3,000 annually in the mid-1970s to more
than 9,000 in 2002.
More room is also required so that women's health programs
can expand.
The 18-level facility, one below grade, will encompass 938,000
sq. ft. of space on Superior Street. It will be able to accommodate
13,500 births, making it third largest maternity center in
the nation.
A full range of health services will be offered, including
genetics, infertility, cardiology and breast health. About
100 physician offices will be in the hospital.
The facility will have 256 beds, of which 134 will be dedicated
for ante- and post-partum patients and 28 for obstetrics and
gynecology.
There will be 32 labor and delivery rooms, 144 bassinets and
10 operating rooms.
Building in Streeterville
Logistics are playing a major role in the project early on
because of the Streeterville site and the building itself,
Knightly said.
The hospital is located between Superior and Chicago streets
and just west of Fairbanks, an area with a lot of pedestrian
and car traffic. Barricades were put up, and parking lanes
were taken.
Routes were planned for deliveries because substantial truck
deliveries every day will be needed during the height of construction.
The steel-framed structure will have a precast concrete and
curtain wall facade.
Because of the nearness of other structures, an earth-retention
system was required, Knightly said. Three sides will be retained
with slurry walls and the fourth with a steel sheeting system.
Sheeting was installed on one side, rather than a fourth slurry
wall, to avoid causing the collapse of a nearby city sewer
during the sitework.
Wood piling foundations for the support of previous buildings
were removed, but caissons were kept, he said. Transfer beams
were installed to shift building weight to multiple caissons.
Medical systems will be purchased as late as possible in case
new technology becomes available that can be installed.
|
Key
Players
|
|
Owner:
|
Northwestern Memorial HealthCare, Chicago
|
|
Construction Manager:
|
Power Construction Co./Jacobs Facilities, Chicago
|
|
Architect:
|
VOA Associates/OWP/P, Chicago
|
|
Structural Engineer:
|
Thornton-Tomasetti, Chicago
|
|
Mechanical Engineer:
|
Environmental Systems Design Inc., Chicago
|
|
Excavation:
|
Brandenburg Industrial Service, Chicago
|
|
Earth Retention:
|
Case Foundation, Roselle, Ill.
|
Return
to Top of 2004 list
|