| West Campus Cogeneration
Facility Cost: $180 million Madison Gas & Electric
and the University of Wisconsin jointly own the West Campus Cogeneration Facility.
The
facility will provide heating and cooling for the campus and electricity for MGE
customers. It will have a capacity of 150 MW of electricity, 20,000 tons of chilled
water and 500,000 lb./hr. of steam.
Rising energy prices have increased
interest in cogeneration.
The cogeneration process is the simultaneous
production of electricity and thermal energy. The residual thermal energy generated
in the process of producing electrical energy, which is wasted in many electrical
generation facilities, is used in the production of steam heat.
Despite
campus conservation measures that have saved enough electricity to power 2,500
homes, Madison's population and business growth and a societal growth in technology
use are creating increased power demand. New classroom and research structures
on campus are adding to the burden.
The facility features more than 94,000
sq. ft. of piping, some of it 72 in. in diameter. That translates into almost
18 mi. of piping.
Conservation was a key project focus, and 717,000 lbs.
of metal and 288,000 lbs. of concrete have been recycled.
Overcoming
Logistical Issues The equipment was put in place first and the enclosure
was constructed around it.
Special handling was required because the power
equipment is large. For instance, a single steam turbine weighs about 242,000
lbs.
The large pieces were brought into downtown Madison via rail and loaded
onto 120-ft.-long heavy-haul trucks. To avoid traffic and pedestrian snarls, police
escorted the trucks to the site during overnight hours.
A temporary bridge
was installed over the existing Willow Creek Bridge on the Observatory Drive delivery
route.
Putting the plant in the middle of a high-use area required logistical
planning.
Because of a lack of lay-down area, materials came in a just-in-time
manner.
Some materials were obtained from far-flung destinations like
Austria, France and Texas.
The facility's size in proportion to the small
site and neighboring structures was a major design challenge.
Studies were
done to determine how the facility, which reaches heights of 117 ft., would cast
shadows during different times of the day and year. Materials were also selected
to break down the building's mass and create a friendlier scale.
Precast
ribbed panels form the building and were chose because of the economics, lack
of lay-down space and difficulty erecting scaffolding for traditional brickwork.
Return
to Top of 2005 list |