| Start 2: Weston Power Plant Unit
4 Cost: $752 million The increasing demand for
electricity is driving the 530-MW Weston Power Plant Unit 4 project in the Central
Wisconsin towns of Kronenwetter and Rothschild.
Low sulfur coal from Wyoming's
Powder River Basin was selected as the fuel to drive a turbine that will produce
Unit 4's energy, said Philip Hayes, project manager for Green Bay-based Wisconsin
Public Service Corp., the owner.
The choice of fuel has environmental
benefits over alternative coals because fewer oxides are released in the air after
low sulfur coal is burned.
Systems will be installed to ensure air quality,
including a selective catalytic reduction unit, a dual train dry scrubber, baghouse
and mercury control system that is reportedly the first of its kind in Wisconsin.
Emissions
will be "very restrictive" in nitrous oxides, sulfur and mercury, Hayes
said. For instance, the plant will produce an average of about 0.06 lbs. of NOx
per million British thermal units of fuel over a 12-month period.
About
10 structures will be built, including a water treatment facility, lime preparation
building and 500-ft.-high stack. The biggest structures will be the boiler and
turbine buildings.
A substantial amount of sitework went into the project.
After
topsoil was removed, an engineered soil was laid beneath the turbine and boiler
buildings. The engineered soil provides resistance against the buildings' differential
settlement due to the heavy loads inside.
"There are voids between
the sand granules, so it (the engineered fill) makes the sand particles adhere
to each other," he said.
About 15,000 tons of fly ash was mixed with
the local sandy soil, Hayes said. Winter Concrete
Pouring Cold weather concrete forming techniques were used to make the continuous
foundation for the boiler and turbine buildings.
About 65,000 cu. yds.
of concrete will be used to form the foundation that is about 300 ft. long, 200
ft. wide and 8 ft. deep.
The forming techniques included warming the aggregate
and water used in the mixing, erecting a tent and using heaters.
About
11,000 tons of structural steel will be used to form the structure, and the erection
was expected to start in May. Once the steel is erected, the boiler and turbine
can be installed.
Unit 4 will connect to the Gardner Park Road substation
that will link to the Arrowhead-Weston transmission line under construction between
Wausau and Duluth, Minn. Return
to Top of 2005 list |