News
 Association
 Law/Courtroom
 Building
 Design
 Infrastructure
 Personnel
 Illinois
 Indiana
 Wisconsin
 Submit News





Construction Law - November 2003

'Best Value' Public Procurements; Substantially Lowest Price Might Not Equal Winning Offer
by John S. Mrowiec

Most of our readers are familiar with local government public construction procurements under the "lowest responsive responsible bid" standard. We discussed those procurements in the August 2002 article, "Protesting Local Public Contract Bids: Who Is the Lowest Responsive Responsible Bidder?"

In a lowest responsive responsible bid procurement, provided the lowest bid is responsive (really not materially unresponsive) and the bidder is responsible, the bidder with the lowest price bid normally must be awarded the contract.

The federal government often uses a different type of construction procurement method, "best value." Under a "best value" procurement, low price is only one of the factors considered by the government. Indeed, low price might not even be the most important factor depending on the terms of the "best value" bid solicitation.

Federal construction contractors are becoming more familiar with "best value" procurements as their use becomes more common. But even those contractors who only pursue state or local public construction might find themselves in a "best value" situation. Some state and local agencies have been authorized to use that procurement method.

A recent case shows that great care in presentation of the bid proposal for submission to the government is critical. Even where the bidder was $5.5 million low, 8 percent lower than the winning bid, the government rejected the low bidder in Fru-Con Construction Co. v. United States, 2003 U.S. Dist. LEXIS 239 (Ct. Cl. Aug. 7, 2003).

The Fru-Con Construction case involved a "best value" solicitation by the architect of the U.S. Capitol for expansion of the West Refrigeration Plant at the Capitol. The "best value" solicitation required submission by bidders of separate proposals for technical and price criteria.

The solicitation provided, "Technical Evaluation Criteria are more important than price, but as the difference in technical merit between proposals becomes less significant, the relative importance of the proposed prices will increase."

The architect did not conduct a price evaluation unless he first found that the bidder was technically qualified. The technical evaluation criteria were:

  • General Contractor's Corporate Experience and Past Performance
  • Chiller Manufacturer's Corporate Experience and Past Performance
  • Organization and Key Personnel
  • Management Plan
  • Subcontractor Management Capabilities
  • Chillers

    The architect rated bidders "Acceptable" or "Unacceptable" on all six factors.

    Minor deficiencies or weaknesses easily correctable would not result in an "Unacceptable" rating. Major or extensive deficiencies would.

    The six technical factors had equal weight but "[a] rating of Unacceptable or Marginal for any factor will deem the overall technical proposal unacceptable or marginal.
    Award shall not be made to a contractor with a Marginal or Unacceptable rating."

    The architect determined that the low bidder's proposal was unacceptable in four of the six technical areas: General Contractor's Corporate Experience and Past Performance; Organization and Key Personnel; Management Plan; and Subcontractor Management Capabilities.

    The low bidder's price proposal was for $61.7 million. The accepted bidder's price proposal was for $67.2 million, a bid that was $5.5 million higher. The architect rejected the low bidder's proposals.

    The low bidder filed a bid protest with the General Accounting Officer. Another bidder also protested but in the U.S. Court of Federal Claims. The court dismissed the other bidder's case and then decided the low bidder's case. The low bidder asked to enjoin the construction and to order the contract awarded to the low bidder.

    The Fru-Con Construction court first listed the legal standards to be applied to any federal procurement bid protest. These standards provide that the court will uphold an agency's decision unless low bidder shows that it is "arbitrary, capricious, an abuse of discretion, or otherwise not in accordance with law" (5 U.S.C. §706(2)(A); 28 U.S.C. §1491(b)(4)). A court may not interfere with an agency's procurement decision unless "it is clear that the agency's determinations were irrational and unreasonable" (Acra, Inc. v. United States, 44 Fed. Cl. 288, 293 (1999) (citation omitted)). Government agencies have wide discretion in determining whether an offer meets technical requirements of a solicitation (CW Govt Travel, Inc. v. United States, 53 Fed. Cl. 580, 590 (2002); see E.W. Bliss Co. v. United States, 77 F.3d 445, 449 (Fed. Cir. 1996)).

    The protesting bidder must show that the agency's evaluation was arbitrary and capricious and that the bidder was prejudiced in the process (CCL Serv. Co. v. United States, 48 Fed. Cl. 113, 120 (2000)). The fact that a bidder disagrees with the evaluator's conclusions is not enough for a court to overturn them (ITT Fed. Servs. Corp. v. United States, 45 Fed. Cl. 174, 185-186 (1999); CRC Marine Servs., Inc. v. United States, 41 Fed. Cl. 66, 83-84 (1998)). A court will not substitute its judgment for that of a contracting officer in such circumstances (ManTech Telecom & Information Sys. Corp. v. United States, 49 Fed. Cl. 57, 63 (2001)). The protesting bidder must show that the government's procurement decisions had no rational basis (Delbert Wheeler Constr., Inc. v. United States, 39 Fed. Cl. 239, 247 (1997)).

    Regarding the specifics of the case, the low bidder complained that it had substantial construction experience and that it could easily correct missing or generic information.
    The government disagreed, noting that the low bidder had not tailored its proposal to the West Refrigeration project, did not include appropriate organization charts, a top manager's resume or detailed subcontractor plans and most of the low bidder's experience on chiller plants was as a subcontractor not a prime contractor.

    The Fru-Con Construction court rejected the low bidder's protest:

    "We do not question low bidder's ability or experience. The issue is whether the defendant acted reasonably in deciding that [the low bidder's] proposal was Unacceptable in that it did not meet the specific and detailed requirements of the Agency's Solicitation. It is important to the procurement process that all bidders submit offers according to the same rules. Adequate written proposals are central to efficient procurement of services. This is particularly true of a complex project such as this, where the offeror's price is secondary to its technical expertise.

    "This was partly because low bidder's 'cut and paste' method was not an effective approach to submitting a proposal that it should have tailored to this job. The administrative record and counsel's arguments at oral argument support the Agency's misgivings."

    The lessons of Fru-Con Construction are match carefully the proposal contents to the Solicitation's requirements and do not count on a better price saving a carelessly assembled technical proposal.


    John S. Mrowiec is a partner with Chicago-based Conway & Mrowiec, a construction and public contracts law and litigation practice. He may be reached at (312) 658-1100. For information, go to the firm's Web site at www.cmcontractors.com.


  •  Click here for more Construction Law News >>



    advertisement


     


    Sponsors

    © 2008 The McGraw-Hill Companies, Inc.
    All Rights Reserved