News
 Association
 Law/Courtroom
 Building
 Design
 Infrastructure
 Personnel
 Illinois
 Indiana
 Wisconsin
 Submit News





Construction Law - January 2006

Sidestepping a General Contractor's Backcharge Backfired


By John S. Mrowiec


Suppose a project owner has not made final payment to a general contractor, and the general contractor has not made final payment to one or more subcontractors. An unpaid subcontractor could record a mechanics lien claim.

May the owner pay the subcontractor directly to remove the subcontractor's lien claim and receive a credit on the amount the owner otherwise owes the general contractor without the general contractor's consent? The answer depends on the facts. For instance, does it matter that the general contractor claims offsets against the amount otherwise owing to the subcontractor?

Some state mechanics lien statutes permit direct payment to subcontractor lien claimants by owners. Some owner-contractor agreements expressly permit direct owner payments to subcontractors. Sometimes, owners and contractors sign escrow agreements permitting direct payments by the escrowee to subcontractors.

Other contracts do not expressly permit direct owner payment to subcontractors and prohibit the contractor from applying for funds not intended to be paid to a subcontractor.


Parties Caught Unawares

A new case shows how both the owner and subcontractor might be severely penalized where each ignored the general contractor's backcharge claims against the subcontractor when the owner made direct payment to the liening subcontractor, Environmental Energy Partners, Inc. v. Siemens Building Technologies, Inc., 2005 Mo. App. LEXIS 1568 (So. Dist., Oct. 25, 2005).

Siemens Building Technologies, Inc. involved a project to upgrade the lighting and to install a new boiler and controls, new drives for the HVAC system and digital controls at a hospital. The owner, St. John's Regional Medical Center, contracted with a general contractor, Environmental Energy Partners Inc., for the work. The general contractor subcontracted the HVAC drives and controls, approximately 40 percent of the total work, to Siemens Building Technologies Inc., as the controls subcontractor.

The project schedule was based on a schedule developed by the controls subcontractor. The subcontract contained a billing schedule and clauses that conditioned final payment to the controls subcontractor on submission of project documentation by subcontractor and prior payment from owner to general contractor.

The subcontract also contained a liquidated damage provision of $250 per day for the controls subcontractor's delay in achieving a Nov. 30, 1998, final completion.

Performance of the subcontract began in April 1998. After Aug. 10, 1998, the controls subcontractor ceased its progress reports to the general contractor and did not return telephone calls or otherwise communicate with the general contractor.

Through September 1998, the owner made nine of the 10 scheduled payments to the general contractor. The owner withheld the tenth payment pending completion of the control subcontractor's work to be evidenced by a completion certificate.

The contractor advised the subcontractor of owner's withholding, but that owner had agreed to release payment to the general contractor if a reasonable completion date were provided. The controls subcontractor did not provide a new completion date.

The decision is unclear on the date, but the controls subcontractor submitted a final invoice for $201,000. Apparently, the controls subcontractor had not been invoicing consistent with the billing schedule in the subcontract.

A Lien Filed

In March 1999, the controls subcontractor provided notice of intent to file a mechanics lien. The general contractor advised the owner that the general contractor would indemnify the owner against the lien claim, remarked that it was fortunate that the owner was withholding payment and said the controls subcontractor would be terminated if it did not provide a completion date. Importantly, the general contractor advised owner of general contractor's intent to seek liquidated damages from the controls subcontractor.

On June 22, 1999, the owner contacted the controls subcontractor to inquire whether the project could be completed by July 1. Instead of a response, the controls subcontractor recorded its mechanics lien on July 1, 1999, and filed suit two weeks later for foreclosure of the lien claim on the owner's property and for breach of contract against the general contractor.

In January 2000, the owner reported that the controls subcontractor had stated that the controls subcontract was complete. Sometime prior to Jan. 24, 2000, counsel for the owner contacted the general contractor to say that the controls subcontractor had informed counsel that the work was complete.

The general contractor advised the controls subcontractor in writing of the conversation, required a signature on the completion certificate required by the subcontract and advised that payment awaited the signed certificate and other documentation. The general contractor forwarded to the owner a copy of the correspondence asking the owner also to sign a counterpart of the completion certificate.

In response to the general contractor's letter, the owner's counsel asked the general contractor whether the general contractor would waive its liquidated damages claim against the controls subcontractor. The general contractor said it would have to consult its attorney. The general contractor decided it could not agree to forego the liquidated damages and so advised the owner. Neither controls subcontractor nor owner forwarded a signed certificate of completion at that time.

On Aug. 15, 2000, the trial on subcontractor's claims began. That morning, the general contractor received the certificate of final completion in the form of a letter from the owner dated Aug. 8, 2000. The general contractor also learned that the owner and controls subcontractor had entered into a settlement agreement, the terms of which were confidential.

The terms of the settlement were that owner paid directly to subcontractor the $148,475 amount withheld from the general contractor; the controls subcontractor would dismiss its mechanics lien foreclosure at a time selected by control subcontractor's attorneys and would indemnify owner from claims arising from the direct payment.

At the trial, the controls subcontractor first was awarded the $52,703 difference between its $201,000 unpaid invoice less owner's direct payment of $148,475. But the general contractor was awarded a $154,250 off-set for liquidated damages against the amount owing subcontractor. The off-set was merely a charge against the sum sought and not an independent counterclaim.

(The general contractor thought its off-set was going to be against a $201,000 claim, not the reduced $52,703 claim after the surprise owner direct payment.) Because the off-set exceeded the award to the controls subcontractor, the general contractor was short $101,546.

'Tortious Interference'

As a result, the general contractor sued the owner for breach of contractor and the controls subcontractor on, among other theories, tortious interference with the contract between owner and general contractor. The general contractor sought the $101,546 shortfall plus interest from the owner and actual and punitive damages from the controls subcontractor.

At a second trial, this time on the general contractor's claims, the jury entered a verdict in favor of the general contractor. The jury awarded the shortfall plus interest against the owner and actual damages and punitive damages against the controls subcontractor. The trial court eliminated the punitive damages awards on all but $500,000 for the general contractor's tortious interference count.

All parties appealed. The appellate court affirmed on most questions for the general contractor. The outcome was that general contractor was entitled to recover from the owner the shortfall in its liquidated damages that otherwise would have been recovered from the subcontractor. Subcontractor also was ordered to pay $500,000 in punitive damages to the general contractor.

The owner argued that general contractor accepted the owner's direct payment to the subcontractor as "substituted performance" of owner's obligation to pay general contractor. The Siemens Building Technologies, Inc. court disagreed. The general contractor had no knowledge of the payment until the first trial began and was damaged because general contractor only owed the subcontractor $46,928, after deduction of liquidated damages, not the $148,475 paid directly by owner to subcontractor.

The result is that the owner had to pay that $101,467 to general contractor. If owner had not made the direct payment, the owner would not have had to pay the $101,467 difference.

The controls subcontractor argued that it had not tortiously interfered with the owner-general contractor contract because control subcontractor's actions in seeking direct payment by owner "were justified." The Siemens Building Technologies, Inc. court disagreed, relying on the payment language in the general contract and the subcontract:

The contract between [owner] and [general contractor] required payment to be made to [general contractor]. The [sub]contract between [controls subcontractor] and [general contractor] provided that until [general contractor] was paid, [subcontractor] was not entitled to payment from [general contractor]. The [sub]contract between [controls subcontractor] and [general contractor] further required [subcontractor] to submit written requests for payment and certificates of completion and to cooperate with [general contractor] in its dealings with [owner] with respect to issues regarding payment. . . . By reason of the provisions of its [sub]contract with [general contractor], [subcontractor] lacked the legal right to cause [owner] to divert the payment that was to be paid to [general contractor] to [subcontractor] (Siemens Building Technologies, Inc., 2005 Mo. App. LEXIS 1568, * 26-27.)

The owner's and control subcontractor's plot to sidestep the general contractor's backcharge backfired. Each of owner and controls subcontractor suffered an expensive lesson.


John S. Mrowiec is a partner with Chicago-based Conway & Mrowiec, a construction and public contracts law and litigation practice. He may be reached at (312) 658-1100. For information, go to the firm's Web site at www.cmcontractors.com.

 


 Click here for more Construction Law News >>



advertisement


 


Sponsors

© 2012 The McGraw-Hill Companies, Inc.
All Rights Reserved