|
Full Subcontractor Payment Defeats Lower Tier Sub's Timely Lien Claim By
John S. Mrowiec
General contractors typically owe an indemnity
to the project owner from subcontractor and lower-tier mechanics lien claims (or,
in Wisconsin, "construction lien.")
A frustration for general
contractors comes when, after payment to a subcontractor, a lower-tier subcontractor
or supplier serves a timely lien notice demanding payment.
If the subcontractor
had advised the general contractor of the sub-subcontractor or supplier, the general
contractor almost certainly would have demanded a lien waiver for that claimant
prior to payment to the subcontractor. Now, the general contractor is being asked
to "pay twice," once to the subcontractor and again to the lower-tier
lien claimant.
A 60- or 90-day payment delay is not uncommon especially
for final payment.
Understandably, most suppliers and subcontractors -
like first tier subcontractors and general contractors - are not anxious to rush
to serve a notice or to record a lien. There is expense involved and customer
relations to consider.
Most construction project participants understand
that there are deadlines for the service of notices of subcontractor and lower-tier
lien claims. These deadlines are understood, in most cases, as establishing the
outside time by which the subcontractor or lower-tier claimants may legally claim
a lien on project funds or real property.
Consequently, subcontractor and
lower-tier sub-subcontractors and suppliers believe they "can wait"
until just near the deadline to serve a notice and still preserve the right to
a lien.
Is meeting the statutory deadline a guarantee that a properly prepared
lien claim will protect a sub-subcontractor when the subcontractor has not paid
the sub-subcontractor? Does the answer depend on whether the general contractor
fully paid the subcontractor (who owes the lower-tier clamant) before the claimant
serves its timely notice? What if the general contractor "might have known"
of the sub-subcontractor's existence and potential claim before the general contractor
paid the subcontractor in full?
Those were the questions in the new decision
in Lazar Brothers Trucking, Inc. v. A & B Excavating, Inc., 2006 Ill. App.
LEXIS 277 (1st Dist. April 7, 2006). No doubt, the result was surprising to the
sub-subcontractor lien claimant and welcomed by the general contractor.
Liens Waived A developer, Schmidt & Associates Construction
Inc., developed land it owned in Northbrook, Ill. The developer decided to act
as its own general contractor and entered into a written contract with A &
D Excavating for excavation work for a $25,000 contract price.
The excavator
provided a waiver of lien acknowledging receipt of a $20,000 payment and provided
a sworn contractor's statement that the excavator had employed no subcontractors.
Likewise, with a second payment of $5,000, the excavator provided a lien waiver
and a sworn statement that listed no subcontractors.
Finally, in relation
to some extra work, the general contractor paid the excavator an additional $4,200.
The excavator provided a final lien waiver and another sworn contractor's statement
listing no subcontractors. The contractor's final payment to the excavator was
on April 11, 2003.
Concurrently, the contractor had contracts with other
trades and was receiving a fee from the owner for the general contracting services.
Unknown Sub Hired Despite the sworn statements from
the excavator, the excavator had engaged a trucking firm, Lazar Brothers Trucking
Inc., to remove excavated materials for the excavator. On April 14, 2003, the
trucking firm recorded a notice of mechanics lien against the property and on
April 16, 2003, served the owner and general contractor with notice of the lien.
The trucking firm contended it was owed $29,200.
Under the Illinois Mechanics
Lien Act, a subcontractor or lower-tier claimant must serve its notice to the
owner (and owners) within 90 days of that claimant's last labor or material supplied
for which the claim is made. (Otherwise, a subcontractor claimant may rely on
the general contractor's statement to the owner as providing the notice required,
but only to the extent of the amount listed as remaining due to the subcontractor.)
The
trucking firm claimed its last work was on Jan. 17, 2003. Accordingly, the trucking
firm's lien notice was timely.
At the time of service of the trucking firm's
notice, the general contractor had paid the excavator in full, the owner had paid
general contractor for its own line items and $53,000 remained owing for the work
of the subcontractors for landscaping, paving, curb and gutter work.
The
trucking firm sued to foreclose its lien claim. The owner/general contractor moved
to dismiss, contending the trucking firm could maintain no lien because the excavator
had been paid in full.
In support of its motion, the owner/general contractor
provided an affidavit stating that the excavator had not informed the general
contractor of a subcontract with the trucking firm and that the general contractor
did not learn of the trucking firm's work until the trucking firm's service of
the notice of lien.
In response, the trucking firm submitted its own affidavit
which stated that the custom and usage in the industry is that the trucking and
removal of debris is the more expensive part of the excavation work, when compared
to excavation site work, and is typically performed contemporaneously with the
excavation. The trucking firm's affidavit continued that the general contractor
knew that the trucking firm was providing the trucking and removal of debris because
(a) the trucker operated approximately 40 trucks, all with the name on the doors,
over a two-day period, and (b) "upon best information and belief" the
general contractor's agents or employees were on site at the time of the trucking
and removal of debris.
Ruling for General Contractor The
trial court ruled in favor of the owner/general contractor and dismissed the trucking
firm's complaint.
On appeal, the trucking firm argued that the trial court
should not have dismissed its complaint because the owner/general contractor was
obligated to establish facts that proved that the owner/general contractor acted
in good faith when it paid the excavator.
The appellate court first set
out the basic rules. To protect itself from paying twice for the same work, the
owner must demand from the contractor, prior to payment, a sworn statement listing
all subcontractors providing labor and materials to the contractor (770 ILCS 60/5).
The contractor's affidavits and lien waivers do not protect the owner if the owner
has notice that the affidavits are false, Lazar Bros. Trucking, 2006 Ill. App.
LEXIS 277, * 6, citing Knickerbocker Ice Co. v. Halsey Bros. Co., 262 Ill. 241,
245, 104 N.E. 665 (1914).
If a subcontractor wishes to protect its rights,
the subcontractor must provide timely written notice to the owner of the amount
owed to the subcontractor for work on the project (770 ILCS 60/24). The subcontractor
has the right to file its lien once it agrees to work on the project (770 ILCS
60/24). If the owner makes proper payments to the contractor prior to receiving
notice of the subcontractor's claim, even timely notice from the subcontractor
may not protect the subcontractor. Lazar Bros. Trucking, 2006 Ill. App. LEXIS
277 * 7, citing 770 ILCS 60/5, 21; Contractors' Ready-Mix, Inc. v. Earl Given
Construction Co., 242 Ill. App. 3d 448, 458, 611 N.E.2d 529 (4th Dist.) app. denied,
152 Ill. 2d 556 (1993).
Reviewing the facts, the Lazar Bros. Trucking appellate
court agreed with the trial court that the owner/general contractor had demanded
and received the statutory sworn statement from the excavator. The excavator's
sworn statement falsely failed to list the trucking firm as a subcontractor. At
the time of the sworn statements from the excavator, the trucking firm had not
served notices of its right to payment for any work related to excavation.
Unable
to contest those facts, the trucking firm argued that the owner/general contractor
was obligated to present evidence proving that it relied on the affidavits in
good faith.
The court disagreed. The sworn statements from the excavator
gave the owner/general contractor "a prima facia defense," Lazar Bros.
Trucking, 2006 Ill. App. LEXIS 277 * 8, citing William Aupperle & Sons, Inc.
v. American National Bank & Trust Co., 28 Ill. App. 3d 573, 576, 329 N.E.2d
458 (3d Dist. 1975). Once the owner had raised the sworn statements as a defense,
the trucking firm claimant had the burden to avoid the effect of those waivers.
To
avoid the dismissal in the face of the sworn statements, the trucking firm needed
to present evidence of a genuine issue of material fact as to whether the owner/general
contractor reasonably relied on the sworn statements, Lazar Bros. Trucking, 2006
Ill. App. LEXIS 277 * 8, citing Merchant's Environmental Industries, Inc. v. SLT
Realty Ltd. Partnership, 314 Ill. App. 3d 848, 866, 731 N.E.2d 394 (1st Dist.
2000).
The trucking firm argued that the owner/general contractor actually
had paid the excavator $20,000 of the original $25,000 contract price in advance
of work. The appellate court did not find that advance payment to represent any
knowledge by owner/general contractor that excavator falsely swore it had no subcontractors.
Similarly,
the trucking firm's arguments that the owner/general contractor must have known
of the trucking firm based on custom and usage in the industry did not apply in
this case. The trucking firm's affidavit that the owner/general contractor saw
the trucks was "on best information and belief." That is not "personal
knowledge" and, therefore, insufficient to raise the necessary question of
fact to avoid dismissal.
The trucking firm contended that it still was
entitled to a lien because the owner had not paid the general contractor in full
at the time of service of the claimant's notice. The Lazar Bros. Trucking appellate
court said that "it was unrebutted" and that the owner made no payments
to its general contractor after March 2003. The general contractor's own sworn
statement showed no balance due on the general contractor's fee line item.
However,
the appellate court did not address the $53,000 owed to other trades at the time
of service of the trucking firm's notice.
Instead, the Lazar Bros. Trucking
court held that the sworn statements, because owner/general contractor had "fully
paid for excavation work before [claimant trucking firm] filed its mechanics lien,
established a defense to the foreclosure action," Lazar Bros. Trucking, 2006
Ill. App. LEXIS 277, * 12.
Thus, the trucking firm had no lien claim even
though it had timely served its notice and recorded its claim and even though
the owner/general contractor owned other trades. The key was that the subcontractor
through whom the claimant claimed had been paid in full with proper sworn statements
from the general contractor to the owner without owner knowledge of the trucking
firm's right to payment.
The lesson is that a lower-tier lien claimant
in Illinois who waits too long, even though not as long as the statutory deadline,
might be too late to claim a lien. John
S. Mrowiec is a partner with Chicago-based Conway & Mrowiec, a construction
and public contracts law and litigation practice. He may be reached at (312) 658-1100.
For information, go to the firm's Web site at www.cmcontractors.com. |