|
Payment Bond Defines Claimants, Deadlines
By John S. Mrowiec
Each of the states in our readership area have adopted payment
bond statutes requiring prime contractors to submit labor
and material payment bonds on public works projects, 30 ILCS
550/2 (Illinois Public Construction Bond Act), I.C. Section
8-23-9-9 (Indiana State Highway Contracts), I.C. Section 36-1-12-14
(Indiana Local Government, Public Construction), R.S. Mo.
Section 107.170 (Bonds of Officers and Contractors for Public
Works), Wis. Stat. Section 779.14 (Public Works Bond). Those
statutes define a proper claimant and the deadline to sue
on the bond.
The form of bond submitted by prime contractors sometimes
is mandated by the contract. Other times, the surety or contractor
uses a standard form. One form is the American Institute of
Architects' A312 bond form.
What happens if the language of the bond provides broader
coverage or a longer time to sue than does the statute? Does
the claimant get the broader coverage or longer time to sue
or does the statute always govern? An Illinois appellate court
recently addressed that question in Carroll Seating Co. v.
Verdico, 2006 Ill. App. LEXIS 1190 (1st Dist., Dec. 21, 2006).
Deadline Question
P. B. Verdico Inc. was the general contractor for renovation
and construction of several school buildings for School District
87 in Berkeley, Ill.
The general contractor submitted the payment bond required
by the Illinois Public Construction Bond Act, 30 ILCS 550/2,
for local government public improvements. The bond was issued
by Travelers Casualty and Surety Co. of America as surety.
The form of the bond was the American Institute of Architects'
A312 form.
The Illinois bond statute provides a time limit for suit of
not "later than 6 months after acceptance by the State
or political subdivision thereof of the building project or
work," 30 ILCS 550/2.
The American Institute of Architects' A312 bond form has a
different deadline for suit in Paragraph 11.
It provides that suit must be commenced within one year after
the earlier of (1) the date the bond claimant gave notice
under the Bond (and direct subcontractors need not give that
notice under the language of the bond) or (2) the date on
which the last labor or service was performed by anyone or
the last materials or equipment were furnished by anyone under
the Construction Contract.
The AIA A312 bond form's suit deadline language continues:
"If the provisions of this Paragraph are void or prohibited
by law, the minimum period of limitations available to sureties
as a defense in that jurisdiction of the suit shall be applicable."
In Verdico, a number of subcontractors sued on the bond. One
of the claimants, Carroll Seating, moved for summary judgment.
The trial court granted the motion and ordered the surety
to pay.
Shareholders of the general contractor had signed indemnity
agreements in favor of the surety and so would owe the surety
for surety's payment of the claim. Those indemnitors intervened
and asked the trial court to reconsider its decision.
The intervenors argued that the claimant should not be granted
summary judgment because, as to that claimant, the suit was
filed more than six months after the owner accepted the project
and, therefore, the suit was untimely. The intervenors contended
the statute, not the language of the bond, must apply.
The trial court disagreed.
Suit Appealed
The intervenors appealed. They argued both the suit deadline
Paragraph 11 in the bond and a separate Paragraph 13 which
provides:
"When this Bond has been furnished to comply with a statutory
or other legal requirement in the location where the construction
was to be performed, any provision in this Bond conflicting
with said statutory or legal requirement shall be deemed deleted
herefrom and provisions conforming to such statutory of other
legal requirement shall be deemed incorporated herein. The
intent is that this Bond shall be construed as a statutory
bond and not as a common law bond."
Read together, Paragraphs 11 and 13 of the bond, intervenors
argued, meant the Public Construction Bond Act's claim-filing
provisions always were required to apply. The Verdico appellate
court held that the statute's claim-filing deadline was "not
mandatory for all public works bonds for two reasons,"
Verdico, 2006 Ill. App. LEXIS 1190, *9.
First, where the legislature intended to mandate the inclusion
of the statutory provisions into all public works bonds, it
did so expressly in 30 ILCS 550/1.
However, the statute did not expressly mandate that the suit
deadline be included in the bond.
Second, and more convincingly, Verdico reasoned that "this
court has consistently found that due to the Bond Act's remedial
nature, parties to a public works bond 'are free to contract
for protection that exceeds the [Act's] minimum'" Verdico,
2006 Ill. App. LEXIS 1190, *10 (citing cases).
The claimant had submitted an affidavit regarding the date
of its claimed last work. That work apparently was "warranty
or remediation work" and not "substantive work."
It did not qualify for "last work."
Nevertheless, the claimant had submitted an affidavit from
another claimant, the mechanical subcontractor. That subcontractor
had performed "balancing work" 11 months later than
the other claimant's nonqualifying work. The affidavit was
uncontested.
Because the bond provided that suit deadline was one year
after service was performed by "anyone" "under
the Construction Contract," the suit was timely for all
of the claimants under Paragraph 11 of the bond, Verdico,
2006 Ill. App. LEXIS 1190, *16-17.
While the contexts have not always been that of deadline to
sue on the bond, courts in our readership area beyond Illinois
have held that the language of a bond given to satisfy a public
construction statute's requirements may expand-but not contract-the
statutory requirements for public construction bonds to the
benefit of claimants. See, e.g., Dow-Par, Inc. v. The Lee
Corp., 644 N.E.2d 150, 155 (Ind. Ct. App. 4th Dist. 1994);
Hilton v. Universal Construction Co., 202 Mo. App. 672, 679,
216 S.W. 1034, 1037 (1919).
Thus, both those claiming and defending on public works payment
bonds must read the bond to determine whether the bond has
given greater rights to the claimant than the statute does.
John S. Mrowiec is a partner with
Chicago-based Conway & Mrowiec, a construction and public
contracts law and litigation practice. He may be reached at
(312) 658-1100. For information, go to the firm's Web site at
www.cmcontractors.com.
|